Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Mission Bay Blvd Quick-Build Project
Not stated
SFMTA · Bike, walk or safety · Implementation / Construction · Under way, ends 31 Aug 2026
10 of the project's 11 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA lists it as a bike project, but does not say whether it builds that bikeway.
- Streets
- Mission Bay Dr, 7th St, Mission Bay Blvd South, Mission Bay Blvd North, Mission Bay Cir
- Planned bikeway
- Separated bikeway, 0.46 mi on Mission Bay Dr, 7th St
Bikeway of undecided type, 0.18 mi on Mission Bay Blvd South, Mission Bay Blvd North
Shared street, 0.045 mi on Mission Bay Cir - Would reach
- No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 10 street segments that lack one. Closer in: 648 residents (2020 census) with none within about one block (440 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation Fall 2025 Fall 2025 Construction Summer 2026 Summer 2026 - Sources disagree
- The published end date, 2026-08-31, has passed; SFMTA's project layer still gives it as Implementation / Construction.
- Records
- SFMTA project page
City decisions naming this project
- ESTABLISH – CLASS IV PROTECTED BIKEWAY Mission Bay Drive, eastbound, from Berry Street to Mission Bay Circle Mission Bay Drive, westbound, from Mission Bay Circle to Berry Street 14(b). ESTABLISH – STOP SIGNS A. Mission …6 Mar 2026 · Engineering hearing · Revised approval path. Approved by the City Traffic Engineer for implementation.
4 milestones and events from the project's own page
- ConstructionSummer 2026 · Project page timeline · Pending
- Engineering Public Hearing Meeting, March 6, 20266 Mar 2026 · Project page event
- DesignWinter-Spring 2026 · Project page timeline · Completed
- OutreachFall 2025 · Project page timeline · Completed
11 decisions on the same streets, not naming this project
- Award Contract No. WW-757R, Laguna, Howard, and Mission Creek Combined Sewer Discharge Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $7,296,786, wit…13 May 2025 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES 4th Street, east side, from 10 feet to 30 feet south of Mission Rock Street (Supervisor District 6) (Approvable by the City Traffic Engineer) Grant Brokl, [staff email rem…18 Apr 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- RESCIND – NO PARKING ANY TIME, EXCEPT BICYCLES 4th Street, east side, from 17 feet to 40 feet north of Minna Street 8(b). ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Minna Street, south side, from 122 feet to 143 fe…7 Mar 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 4th Street, west side, from 19 feet to 50 feet north of King Street (31-foot bike share station) (Supervisor District 6) (Approvable by the City Tra…14 Jun 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH - NO PARKING ANY TIME, EXCEPT BICYCLES 4th Street, east side, from 17 feet to 40 feet north of Minna Street (Supervisor District 6) (Approvable by the City Traffic Engineer) Jason Hyde, [staff email removed — s…19 May 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 5th Street, west side, from 6 feet to 92 feet south of Howard Street (86-foot bike share station with angled plates in floating buffer) (Supervisor D…8 Apr 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 4th Street, west side, from Gene Friend Way to 103 feet northerly (92-foot bike share station with red zones on each side of the station) (Supervisor…5 Nov 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- ESTABLISH - NO PARKING ANYTIME EXCEPT BICYCLES 4th Street, east side, from 103 feet to 144 feet south of Campus Way (Approvable by the City Traffic Engineer) 14(b). ESTABLISH - PASSENGER LOADING ZONE AT ALL TIMES 4th Str…4 Jun 2021 · Engineering hearing · Approved by the City Traffic Engineer to add subsection 14(c) for clarity and tor implementation. #
- Approving temporarily prohibiting the use of northbound 4th Street between Berry and Channel Streets by all vehicles other than transit, buses, bicycles, taxis, and emergency vehicles; directing the City Traffic Engineer…5 Jan 2021 · SFMTA Board · ADOPTED — 5 ayes
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 7th Street, east side, from 4 feet to 54 feet north of Brannan Street (50-foot bike share station) (Supervisor District 6) Pallavi Panyam, [staff ema…16 Oct 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation. The Environmental Review citation, Case 2015-005492ENV, is accurate since temporary station installation and/or relocation are included in the bike share system.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 7th Street, east side, from 17 to 106 feet north of King Street (70-foot bike share station in hatched area) (Supervisor District 6) Laura Stonehill,…18 Oct 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.
7 other projects on these street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 18 shared street segments
- DTX - Mission Bay Dr At Grade Crossingother · Design · 5 shared street segments
- 7th Street and 8th Street Safety ProjectsSFMTA · Completed · 5 shared street segments
- Train Control Upgrade Project - Phase 1Public Works · Design · 5 shared street segments
- Bikeway HardeningSFMTA · Planning · 2 shared street segments
- Brannan Street Safety ProjectSFMTA · Completed · 2 shared street segments
- Various Locations Spot Main Sewer Replacement No 2Public Works · Design · 1 shared street segment
2 documents on the project page
How we built this: About the Data