Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

WD-2922: 8-inch Ductile Iron Water Main Replacement on Lincoln Way and Irving St from Sunset Blvd to 19th Ave and Various Side Streets

0% in published scope

SFPUC · Sewer, water or power · Design · Under way, ends 29 Sep 2030

1 of the project's 3 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
20th Ave, 21st Ave, 22nd Ave, 23rd Ave, 24th Ave, 25th Ave
Planned bikeway
Shared street, 0.78 mi on 20th Ave, 34th Ave, 28th Ave
Would reach
435 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 1,267 residents with none within about one block (440 feet) today would have one; 813 residents with none within about two blocks (880 feet) today would have one
Scope
“8-inch Ductile Iron Water Main Replacement on Lincoln Way and Irving Street from 19th Ave to 36th Ave”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionAug 2026Sep 2030
Sources disagree
The coordination feed gives construction starting 2026-08-07; SFPUC's project page text gives 2027-04 (“Spring 2027”).
The coordination feed gives construction ending 2030-09-29; SFPUC's project page text gives 2029-04 (“Spring 2029”).
The start date has passed (2026-08-07) while the phase is still Design, per the coordination feed.
Records
SFPUC project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

9 decisions on the same streets, not naming this project

Construction on these street segments

2025202620272028202920302031todayWD-2922: 8-inch Ductile Iron Water M…PW Various Locations Sewer Replaceme…Various Locations Sewer Replacement …PEFWS Pipeline Contract F- 24-Inch W…PW Various Locations Sewer Replacement No 18: construction 25 Jun 2025 to 26 Oct 2026Various Locations Sewer Replacement No 30: construction 12 Apr 2027 to 19 Jul 2028PEFWS Pipeline Contract F- 24-Inch Water: construction 1 Jan 2028 to 1 Jan 2030WD-2922: 8-inch Ductile Iron Water Main Replacement on Lincoln Way and Irving St from Sunset Blvd to 19th Ave and Various Side Streets: construction 7 Aug 2026 to 29 Sep 203025 Jun 2025 – 26 Oct 202612 Apr 2027 – 19 Jul 20281 Jan 2028 – 1 Jan 20307 Aug 2026 – 29 Sep 2030

Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.

8 other projects on these street segments