252 street projects under way or coming up on the Biking and Rolling Plan's network.
Mariposa, Lake Merced and Evans CSD Improvements
0% in published scope
Public Works · Sewer, water or power · Design · Under way, ends 30 Oct 2026
1 of the project's 3 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- Evans Ave, Illinois St
- Planned bikeway
- Separated bikeway, 0.49 mi on Evans Ave
- Scope
- “2312i”
- Dates
Start End Public consultation not published not published Construction Dec 2025 Oct 2026 - Sources disagree
- The start date has passed (2025-12-01) while the phase is still Design, per the coordination feed.
- Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Outfall Rehabilitation Projects
City decisions naming this project
- Award Contract No. WW-790, Evans Ave. and Mariposa St. Outfalls Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $2,576,348, with a duration of 379 con…9 Sep 2025 · SFPUC Commission · approve the Consent Calendar
3 decisions on the same streets, not naming this project
- ESTABLISH – TOW–AWAY, NO PARKING ANY TIME A. Evans Avenue, south side, from Rankin Street to 193 feet easterly (removes 7 unmetered parking spaces in the vicinity of rail crossing) B. Evans Avenue, south side, from 483 f…14 Nov 2025 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- 10(a). ESTABLISH – CLASS IV BIKEWAY A. Evans Avenue, south side, from Keith Street to Jennings Street B. Evan Avenue, both directions, from Jennings Street to Hunters Pt. Boulevard C. Hunters Point Boulevard, both direct…4 Dec 2020 · Engineering hearing · To be approved by the City Traffic Engineer for implementation after receipt of environmental clearance.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Evans Avenue, north side, from 67 feet to 146 feet west of Newhall Street (72-foot bike share station with red zones on either side) (Supervisor Dist…24 Jan 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: No comments received.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 1 other project on these street segments publishes no construction dates.
4 other projects on these street segments
- Bayview CBTP Quick-Build ProjectsSFMTA · Completed · 3 shared street segments
- Bayview Community Based Transportation PlanSFMTA · Planning · 3 shared street segments