SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Street Resurfacing Program-BBSR Paving FY 27-28

0% in published scope

Public Works · Repaving · Planning · Starts 1 Jul 2027, ends 30 Jun 2028

Early enough to change: Public Works gives its phase as Planning; its project page may list a contact. No meeting on it is posted for the next 60 days.

The project's one street segment on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
Alvarado St, Anderson St, Andover St, Belgrave Ave, Belvedere St, Dellbrook Ave
Planned bikeway
Shared street, 0.29 mi on Gellert Dr
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJul 2027Jun 2028
Records
Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

1 decisions on the same streets, not naming this project

Construction on these street segments

2024202520262027202820292030todayStreet Resurfacing Program-BBSR Pavi…PW As Needed Main Sewer Replacement …Various Locations Sewer Replacement …PW Various Locations Sewer Replaceme…Various Locations Sewer Replacement …Various Locations Sewer Replacement …PW As Needed Main Sewer Replacement No 10: construction 30 Sep 2024 to 2 Sep 2027Various Locations Sewer Replacement No 25: construction 25 Feb 2027 to 31 Mar 2028PW Various Locations Sewer Replacement No 31: construction 7 Jun 2027 to 9 Jun 2028Various Locations Sewer Replacement No 36: construction 30 Jan 2028 to 1 Apr 2029Various Locations Sewer Replacement No 40: construction 4 Aug 2028 to 4 Aug 2029Street Resurfacing Program-BBSR Paving FY 27-28: construction 1 Jul 2027 to 30 Jun 202830 Sep 2024 – 2 Sep 20271 Jul 2027 – 30 Jun 202825 Feb 2027 – 31 Mar 20287 Jun 2027 – 9 Jun 202830 Jan 2028 – 1 Apr 20294 Aug 2028 – 4 Aug 2029

Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.