Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Transbay Howard Streetscape Improvement Project

Builds 9%

SFMTA with Public Works · Bike, walk or safety · Implementation / Construction · Under way, ends 31 Dec 2028

1 of the project's 17 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 0.15 mi of the plan's bikeway.

Streets
Howard St, The Embarcadero
Planned bikeway
Separated bikeway, 1.9 mi on Howard St, The Embarcadero
Scope
“Transit, sidewalk, and roadway improvements on Howard Street from 4th Street to Embarcadero Street and Stuart Street from Howard Street to Mission Street as part of the Transit Center Soda program. 1297I”
Dates
StartEnd
Public consultationSpring - Fall 20222022-12-07 – 2022-12-21
Construction2026 - 2028Dec 2028
Sources disagree
The project page's timeline and event cards give the latest public consultation as 2022-12-21; the page's text gives 2025-10 (“fall 2025”).
The coordination feed gives construction starting 2025-10-15; SFMTA's project page gives 2026, which is shown.
The coordination feed gives construction ending 2028-10-18; SFMTA's project page gives 2028-12-31, which is shown.
Public Works' page gives its status as In progress; SFMTA's project layer gives Implementation / Construction.
SFMTA gives the phase as Implementation / Construction; the coordination feed gives Construction.
Records
SFMTA project page · Public Works project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

7 milestones and events from the project's own page
22 decisions on the same streets, not naming this project

Construction on these street segments

20232024202520262027202820292030todayTransbay Howard Streetscape Improvem…Northern Waterfront Electrical Impro…Folsom-Howard Streetscape ProjectContract 36 Traffic Signal Modificat…Central Embarcadero Safety ProjectStormwater Trash CaptureNorthern Waterfront Electrical Improvements (NWEI): construction 1 Apr 2023 to 31 Dec 2026Folsom-Howard Streetscape Project: construction 2024 to 31 Dec 2029Contract 36 Traffic Signal Modifications: construction Apr 2024 to 31 May 2026Central Embarcadero Safety Project: construction 2026 to 31 Dec 2028Stormwater Trash Capture: construction 28 Jun 2027 to 24 Mar 2028Transbay Howard Streetscape Improvement Project: construction 2026 to 31 Dec 20281 Apr 2023 – 31 Dec 2026Apr 2024 – 31 May 20262026 – 31 Dec 20282026 – 31 Dec 202828 Jun 2027 – 24 Mar 20282024 – 31 Dec 2029

Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.

8 other projects on these street segments
4 documents on the project page