Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Lower Alemany Area Stormwater Improvement Project
Already built
SFPUC · Sewer, water or power · Design · Starts 2 Jan 2027, ends 30 Jun 2031
All 2 of the project's street segments on planned bikeway streets already have an all-ages bikeway.
- Streets
- Alemany Blvd, Boutwell St, Industrial St
- Planned bikeway
- Separated bikeway, 1.4 mi on Alemany Blvd
- Scope
- “Construction of a new sewer that consists of 5,650 linear feet of 10-ft diameter tunnel, 1000 linear feet of 20 ft x 9-ft box sewer and 42-in diameter sewer.”
- Dates
Start End Public consultation not published not published Construction Jan 2027 Jun 2031 - Sources disagree
- The coordination feed gives construction ending 2031-06-30; SFPUC's project page text gives 2031 (“Early 2031”).
- Records
- SFPUC project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Authorize the General Manager to execute an Installment Sale Agreement to secure a Clean Water State Revolving Fund Loan for the Lower Alemany Area Stormwater Improvement Project14 Jul 2026 · SFPUC Commission · approve Item 9
- Resolution approving Amendment No. 2 to Contract No. PRO.0164, Engineering Services for the Lower Alemany Area Stormwater Improvement Project, between the City, acting by and through the San Francisco Public Utilities Co…10 Sep 2024 · Board of Supervisors · ADOPTED Pass
- Resolution approving Amendment No. 2 to Contract No. PRO.0164, Engineering Services for the Lower Alemany Area Stormwater Improvement Project, between the City, acting by and through the San Francisco Public Utilities Co…4 Sep 2024 · Board of Supervisors, Budget and Finance Committee · RECOMMENDED Pass
- Resolution approving Amendment No. 2 to Contract No. PRO.0164, Engineering Services for the Lower Alemany Area Stormwater Improvement Project, between the City, acting by and through the San Francisco Public Utilities Co…16 Jul 2024 · Board of Supervisors
- Approve Amendment No. 2 to Contract No. PRO.0164, Engineering Services for the Lower Alemany Area Stormwater Improvement Project with McMillen Jacobs Associates25 Jun 2024 · SFPUC Commission · continued
8 earlier
- Amend Contract No. PRO.0164, Engineering Services for the Lower Alemany Area Stormwater Improvement Project23 Jan 2024 · SFPUC Commission · approve items 7a through 7i
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…9 May 2023 · Board of Supervisors · FINALLY PASSED Pass
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…2 May 2023 · Board of Supervisors · PASSED ON FIRST READING Pass
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…26 Apr 2023 · Board of Supervisors, Budget and Finance Committee · RECOMMENDED Pass
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…12 Apr 2023 · Board of Supervisors
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…11 Apr 2023 · Board of Supervisors
- Approve the selection of McMillen Jacobs Associates and award Agreement No. PRO.0164, Engineering Services to support SFPUC engineering services in the design of the proposed Lower Alemany Area Stormwater Improvement Pr27 Jul 2021 · SFPUC Commission · approve the Consent Calendar Item 9a
- Approve the selection of McMillen Jacobs Associates and award Agreement No. PRO.0164, Engineering Services for the proposed Lower Alemany Area Stormwater Improvement Project26 Jan 2021 · SFPUC Commission · approve the Consent Calendar items 10b through 10e
5 decisions on the same streets, not naming this project
- RESCIND – CLASS II BIKEWAY Alemany Boulevard, westbound, from Congdon Street to 520 feet easterly (on freeway overpass) (Requires approval by the SFMTA Board) 35(b). ESTABLISH – CLASS IV PROTECTED BIKEWAY Alemany Bouleva…8 Nov 2024 · Engineering hearing · Clarified approval path, location of 35(a), and 35(b) is a reclassification of an existing Class II facility to a Class IV facility. Items 35(b), 35(c) and 35(d) approved by the City Traffic Engineer for implementation. Item 35(a) approved by the City Traffic Engineer to forward to the SFMTA Board f
- ESTABLISH - CLASS IV BIKEWAY (TWO-WAY PROTECTED) Alemany Boulevard from Stoneybrook Ave/Cambridge Ave to Crescent Ave/Putnam Ave Installed a concrete barrier to protect the existing bikeway on Alemany Boulevard between S…8 Jan 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Alemany Boulevard, east side, from 53 feet to 122 feet south of Francis Street (62-foot bike share station with red zones on either end) (Supervisor …12 Jun 2020 · Engineering hearing · On hold at the request of the District 11 Supervisor. Public Comments: Comments received in support and opposition.
- Resolution approving the First Amendment to the Freeway Maintenance Agreement between the City and County of San Francisco and the California Department of Transportation, to include City's maintenance of bicycle lanes a…9 Jun 2020 · Board of Supervisors · Passed
- ESTABLISH – NO PARKING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Alemany Boulevard, north side, from 100.5 feet to 159.5 feet east of Silver Avenue (52’-5” bike share station with red zones on end of the station) (S…6 Dec 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Bayview Community Based Transportation PlanSFMTA · Planning · 7 shared street segments
- Alemany Bikeway ProjectSFMTA · Completed · 3 shared street segments
- Visitacion Valley and Portola Community Based Transportation PlanSFMTA · Planning · 2 shared street segments
- Alemany Interchange Bike Lanes ProjectSFMTA · Completed · 2 shared street segments
- Excelsior Neighborhood Traffic Calming ProjectSFMTA · Completed · 1 shared street segment
- Various Locations Pavement Renovation with Tracks No 1Public Works · Planning · 1 shared street segment
- Various Locations Sewer Replacement No 39Public Works · Design · 1 shared street segment
- Alemany Interchange Improvement ProjectPublic Works · In progress · 1 shared street segment