Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Various Locations Pavement Renovation No 90

0% in published scope

Public Works · Repaving · Construction · Under way, ends 12 Oct 2027

9 of the project's 12 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
14th Ave, 15th Ave, 23rd St, 7th Ave, Aerial Way, Capitol Ave
Planned bikeway
Separated bikeway, 2.4 mi on Laguna Honda Blvd, 7th Ave
Shared street, 0.37 mi on Laguna Honda Blvd, Corbett Ave, 23rd St
Would reach
4,839 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 9 street segments that lack one. Closer in: 3,306 residents, 1 school with none within about one block (440 feet) today would have one; 3,240 residents, 1 school with none within about two blocks (880 feet) today would have one
Scope
“2441I”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionAugust 2026Oct 2027
Sources disagree
The coordination feed gives construction starting 2026-07-20; Public Works' project page (Start “Summer, 2026”; text “August 2026”), 2026-08, which is shown.
Records
Public Works project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

6 decisions on the same streets, not naming this project

Construction on these street segments

20252026202720282029todayVarious Locations Pavement Renovatio…PW As Needed Spot Sewer Replacement …PW Various Locations Sewer Replaceme…PW Various Locations Sewer Replaceme…Various Locations Sewer Replacement …PW As Needed Spot Sewer Replacement No 47: construction 22 Sep 2025 to 26 Oct 2026PW Various Locations Sewer Replacement (JV VL PR No 77): construction 15 Jun 2026 to 31 Aug 2027PW Various Locations Sewer Replacement (JV VL PR No 90): construction Aug 2026 to 12 Oct 2027Various Locations Sewer Replacement No 27: construction 19 Feb 2027 to 19 Feb 2028Various Locations Pavement Renovation No 90: construction Aug 2026 to 12 Oct 2027Aug 2026 – 12 Oct 202722 Sep 2025 – 26 Oct 202615 Jun 2026 – 31 Aug 2027Aug 2026 – 12 Oct 202719 Feb 2027 – 19 Feb 2028

Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.

6 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.