Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

PW Various Locations Sewer Replacement No 16

Already built

Public Works · Sewer, water or power · Construction · Under way, ends 9 Feb 2027

The project's one street segment on a planned bikeway street already has an all-ages bikeway.

Streets
10th Ave, 16th St, 17th Ave, 17th St, 19th St, 20th St
Planned bikeway
Separated bikeway, 0.12 mi on Valencia St
Scope
“WW-727R, 2227i”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionSep 2025Feb 2027
Records
SFPUC contract page (WW-727R Various Locations Sewer Replacement No.16) · Interagency coordination feed record (DataSF row)

City decisions naming this project

11 decisions on the same streets, not naming this project

Construction on these street segments

2025202720292031203320352037todayPW Various Locations Sewer Replaceme…WW-779 Various Locations Sewer Repla…Bikeway HardeningWD-2919: 8- and 12-Inch Ductile Iron…Street Resurfacing Program- BBSR Pav…Joint - MTA Lead - Fillmore St Pavem…OShaughnessy and Woodside Ave Paveme…Various Locations Pavement Renovatio…WW-779 Various Locations Sewer Replacement No. 32: construction 2 Jun 2025 to 29 Oct 2027Bikeway Hardening: construction 1 Jul 2025 to 30 Jun 2027WD-2919: 8- and 12-Inch Ductile Iron Water Main Replacement on 18th and Mariposa Streets from Potrero Ave. to Texas St. and on Various Side Streets: construction 13 Apr 2026 to 9 Dec 2027Street Resurfacing Program- BBSR Paving FY 26-27: construction 1 Jul 2026 to 7 Jul 2027Joint - MTA Lead - Fillmore St Pavement Renovation Phase 2: construction 11 Oct 2031 to 23 Dec 2032OShaughnessy and Woodside Ave Pavement Renovation: construction 29 Dec 2031 to 12 Mar 2033Various Locations Pavement Renovation Under Overhead Contact System No 4: construction 2 Feb 2035 to 16 Apr 2036PW Various Locations Sewer Replacement No 16: construction 8 Sep 2025 to 9 Feb 20278 Sep 2025 – 9 Feb 20272 Jun 2025 – 29 Oct 20271 Jul 2025 – 30 Jun 202713 Apr 2026 – 9 Dec 20271 Jul 2026 – 7 Jul 202711 Oct 2031 – 23 Dec 203229 Dec 2031 – 12 Mar 20332 Feb 2035 – 16 Apr 2036

Construction start and end as each department publishes them; a dot where only one is published. 1 other project on these street segments publishes no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.