Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Golden Gate Avenue Slow Street
Builds 23%
SFMTA · Bike, walk or safety · Legislated · Under way, no end date published
2 of the project's 8 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 0.13 mi of the plan's bikeway.
- Streets
- Golden Gate Ave, Masonic Ave, Parker Ave
- Planned bikeway
- Shared street, 0.9 mi on Golden Gate Ave, Parker Ave
Separated bikeway, 0.26 mi on Masonic Ave - Would reach
- 0 residents (2020 census), 2 schools would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 1,058 residents with none within about one block (440 feet) today would have one; 466 residents with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation 26 Jan 2022 2 Feb 2022 Construction Jun 2020 not published - Records
- SFMTA project page
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
5 milestones and events from the project's own page
- Golden Gate Avenue Engineering Public Hearing Results (6/10/22 - 6/22/22 Virtual Public Hearing)8 Jul 2022 · Project page notice
- Engineering Public Hearing, June 10, 202210 Jun 2022 · Project page notice
- Jun 10, 2022 Engineering Public Hearing -- Golden Gate Avenue Design10 Jun 2022 · Project page event
- Golden Gate Avenue Slow Street Virtual Open House 2/2/20222 Feb 2022 · Project page event
- Golden Gate Avenue Slow Street Virtual Open House 1/26/202226 Jan 2022 · Project page event
8 decisions on the same streets, not naming this project
- Approve an increase of 155 calendar days to the duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for SFPUC DECEMBER 10, 2024 MEETING MINUTES Page 6 of 1…10 Dec 2024 · SFPUC Commission · approve Item 13
- RESCIND – CLASS III BIKE LANE Baker Street, southbound, from Fell Street to Oak Street 38(b). RESCIND – ANGLED PARKING ESTABLISH – PARALLEL PARKING Baker Street, west side, between Oak Street and Fell Street 38(c). ESTAB…8 Nov 2024 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- RESCIND – CLASS III BIKE LANE Baker Street, southbound, from Fell Street to Oak Street 8(b). RESCIND – ANGLED PARKING ESTABLISH – PARALLEL PARKING Baker Street, west side, between Oak Street and Fell Street 8(c). ESTABLI…18 Oct 2024 · Engineering hearing · Item withdrawn by staff.
- Approve an increase of 90 calendar days to the duration contingency and increase of $200,000 to the amount contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a…25 Jun 2024 · SFPUC Commission
- Approve an increase of 185 calendar days to the contract duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a new contract duration limit of up to 570…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- Accept work performed by Trinet Construction, Inc. for Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair; approve Modification No. 1 (Final) decreasing the Contract amoun…23 Jan 2024 · SFPUC Commission · approve items 7a through 7i
- Award Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair, in the amount of $566,000, and with a duration of 240 consecutive calendar days, to the responsible bidder that s…10 Jan 2023 · SFPUC Commission · Approve Consent Calendar Items 6a through 6j
- Accept work performed by Cratus, Inc. for Contract No. WD-2614, 8-Inch Ductile Iron Water Main Replacement on Green Street from Gough Street to Broderick Street; approve Modification No. 2 (Final), decreasing the contrac…8 Jun 2021 · SFPUC Commission · approve the Consent Calendar 8a through 8e
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Slow StreetsSFMTA · Construction · 4 shared street segments
- Masonic Avenue Streetscape Improvement ProjectPublic Works · In progress · 2 shared street segmentsPublic Works' page gives its status as In progress; SFMTA's project layer gives its phase as Completed.
- PW Various Locations Sewer Replacement No 31Public Works · Design · 2 shared street segments
- Street Resurfacing Program- BBSR Paving FY 26-27Public Works · Construction · 2 shared street segments
- As Needed City-wide Pavement Preservation 6 (General As-Needed Contract G29)Public Works · Construction · 1 shared street segment
- Masonic Avenue Streetscape ProjectSFMTA · Completed · 1 shared street segment
- PW Various Locations Sewer Replacement No 19Public Works · Design · 1 shared street segment
- Various Locations Pavement Renovation No 78Public Works · Design · 1 shared street segment
How we built this: About the Data