Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Channel Force Main Intertie
0% in published scope
SFPUC · Sewer, water or power · Construction · Under way, ends 31 Dec 2026
1 of the project's 2 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- Cesar Chavez Street
- Planned bikeway
- Separated bikeway, 0.21 mi on Cesar Chavez St
- Scope
- “The San Francisco Public Utilities Commission (SFPUC) operates a combined sewer system that collects and treats sewage and stormwater. Our Wastewater Capital Improvement Program is upgrading and modernizing our system to ensure we can continue to protect public health and the environment now and into the future. The Channel Force Main Intertie Project will increase the reliability, provide operational flexibility, and allow for future inspections and maintenance. Summer 2026 Update This year, the project progressed as crews shifted to the 48-inch bypass work connecting the 66-inch Channel Forc”
- Dates
Start End Public consultation not published not published Construction Summer 2023 Dec 2026 - Sources disagree
- SFPUC's project page's Completion field gives construction ending 2026-12-31; SFPUC's project page text gives 2027 (“Early 2027”).
- Records
- SFPUC project page
City decisions naming this project
- Contract No. WW-723R, Channel Force Main Intertie, with Anvil Builders Inc requiring additional pipe modifications and to extend dry weather restricted work into 202628 Apr 2026 · SFPUC Commission · approve Item 13
- Approve an increase of the cost and duration contingency of $2M and 350 calendar days, for Channel Force Main Intertie, with Anvil Builders, Inc.25 Feb 2025 · SFPUC Commission · approve Item 13
- Wastewater Enterprise Quarterly Report including Southeast Area Major Projects Update and Biosolids and Headworks26 Mar 2024 · SFPUC Commission
- Approve the plans and specifications to construct a pipeline connection and valve controls between the Channel Force Main to the existing Islais Creek Transport/Storage Box13 Dec 2022 · SFPUC Commission · approve Item 13 – Resolution 1 to execute the Letter of Agreement with PG&E
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.
4 other projects on these street segments
- Cesar Chavez Bikeway Improvements ProjectSFMTA · Detailed Design · 2 shared street segments
- Bay Corridor Transmission and Distribution Phase 4 and Water ImprovementsSFPUC · Construction · 2 shared street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 2 shared street segments
- Indiana Street Bikeway ProjectSFMTA · Completed · 1 shared street segment