SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

WD-2885 8-Inch Ductile Iron Water Main Replacement, Sewer Replacement, and Paving Renovation on Fulton Street from Great Highway to 31st Avenue and Various Locations

0% in published scope

SFPUC · Repaving · Design · Under way, ends 1 Aug 2028

1 of the project's 2 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
39th Ave, 40th Ave, 41st Ave, 42nd Ave, 43rd Ave, 44th Ave
Planned bikeway
Shared street, 0.26 mi on 43rd Ave
Bikeway of undecided type, 0.26 mi on 47th Ave
Scope
“8-Inch Ductile Iron Water Main Replacement on Fulton Street from Great Highway to 31st Avenue and Various Locations”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionFeb 2024Aug 2028
Sources disagree
The start date has passed (2024-02-03) while the phase is still Design, per the coordination feed.
Records
SFPUC contract page (WD-2885 8-Inch Ductile Iron Water Main Replacement, Sewer Replacement, and Paving Renovation on Fulton St. from Great Highway to 31st Ave. and on Various Side Streets) · Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

10 decisions on the same streets, not naming this project

Construction on these street segments

202420252026202720282029203020312032todayWD-2885 8-Inch Ductile Iron Water Ma…Various Locations Sewer Replacement …PW StreetResurfacingPro-BBSR Pavemen…PW Various Locations Sewer Replaceme…PEFWS Pipeline Contract C - 24-inch …Various Locations Sewer Replacement #21: construction 27 Feb 2024 to 13 Apr 2027PW StreetResurfacingPro-BBSR Pavement Prese FY 26-27: construction 1 Jul 2026 to 7 Jul 2027PW Various Locations Sewer Replacement No 21: construction 2 Oct 2026 to 2 Oct 2027PEFWS Pipeline Contract C - 24-inch 42nd (between Lawton & Irving): construction 1 Jan 2029 to 31 Dec 2031WD-2885 8-Inch Ductile Iron Water Main Replacement, Sewer Replacement, and Paving Renovation on Fulton Street from Great Highway to 31st Avenue and Various Locations: construction 3 Feb 2024 to 1 Aug 20283 Feb 2024 – 1 Aug 202827 Feb 2024 – 13 Apr 20271 Jul 2026 – 7 Jul 20272 Oct 2026 – 2 Oct 20271 Jan 2029 – 31 Dec 2031

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.