Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Transit U Improvement Project
0% in published scope
SFMTA with Public Works · Bike, walk or safety · Implementation / Construction · Under way, ends 22 Jan 2027
6 of the project's 7 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's page for it names no bike work.
- Streets
- Market St, Bush St
- Planned bikeway
- Shared street, 0.64 mi on Market St
Separated bikeway, 0.065 mi on Bush St - Scope
- “1248I”
- Dates
Start End Public consultation 2017-2019 2017-2019 Construction Jan 2025 Jan 2027 - Sources disagree
- SFMTA's project page gives construction starting 2025, a stage it still marks Pending; the coordination feed gives 2025-01-21, which is shown.
Public Works' page gives its status as In progress; SFMTA's project layer gives Implementation / Construction.
SFMTA gives the phase as Implementation / Construction; the coordination feed gives Construction. - Records
- SFMTA project page · Public Works project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Transit U Improvements Project: Extend contract duration by 360 calendar days10 Jul 2026 · Delegated contract change (Public Works) · Contract change approved by the Director
- Transit U Improvement Project – Contract Award17 Oct 2024 · Public Works Commission
5 milestones and events from the project's own page
- Construction2025 · Project page timeline · Pending
- Engineering Public Hearing Meeting, February 18, 202218 Feb 2022 · Project page event
- SFMTA Board of Directors ReviewSummer 2021 · Project page timeline · Pending
- Design2020-2021 · Project page timeline · Pending
- Outreach and Planning via the South Downtown Design + Activation Plan2017-2019 · Project page timeline · Pending
11 decisions on the same streets, not naming this project
- ESTABLISH – SIDEWALK BIKE SHARE STATION Market Street, north side, from 47 feet to 107 feet east of Bush Street (Supervisor District 3) (Approvable by the City Traffic Engineer) Laura Stonehill, [staff email removed — se…19 Jul 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO PARKING ANYTIME EXCEPT BICYCLES Mission Street, west side, from 47 feet to 60 feet south of 21st Street (removes General Metered Parking Space #2506) (Supervisor District 9) (Approvable by the City Traffic…22 Mar 2024 · Engineering hearing · Item withdrawn by staff.
- Accept work performed by D’Arcy & Harty Construction, Inc for Contract No. WW-712, New Montgomery, Jessie, Minna, and Mission Street Brick Sewer Rehabilitation, for a total contract amount of $6,891,778, and with a total…9 May 2023 · SFPUC Commission · approve the Consent Calendar
- RESCIND – NO PARKING ANY TIME EXCEPT BICYCLES ESTABLISH – GENERAL METERED PARKING Mission Street, west side, from 3 feet to 24 feet south of Kingston Street (restore parking meter #3424) 8(b). ESTABLISH – NO PARKING ANY …17 Feb 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of $2,250,000 to the contract cost contingency, and an increase of 180 consecutive calendar days to the contract duration contingency for Contract No. WW-712, New Montgomery, Jessie, Minna, and Missio…8 Feb 2022 · SFPUC Commission · approve Item 10
- Approve an increase of 30 consecutive calendar days to the contract duration contingency for Contract No. WW-703, Mission Street, 16th to Cesar Chavez Street, Brick Sewer Rehabilitation; and authorize the General Manager…14 Dec 2021 · SFPUC Commission · approve Consent Calendar items 10a through 10g
- Approve the plans and specifications, and award Contract No. WW-712, New Montgomery, Jessie, Minna, and Mission Streets Brick Sewer Rehabilitation, in the amount of $4,888,750, and with a duration of 390 consecutive cale…11 May 2021 · SFPUC Commission · approve Consent Calendar items 8c, 8d, and 8g
- Amending Transportation Code, Division II, Section 702 to reduce the speed limit on Market Street between Franklin Street and Steuart Street - designate a transit-only lane on Market Street RESCIND - RIGHT TURN ONLY, EXC…19 Jan 2021 · SFMTA Board · ADOPTED — 5 ayes, 2 nays
- Ordinance ordering the vacation of the sidewalk portion of streets on the south side of Mission Street at the intersection of Mission and Fremont Streets and on the east side of Fremont Street at the same intersection to…10 Mar 2020 · Board of Supervisors · Passed
- Hearing of the Board of Supervisors sitting as a Committee of the Whole on March 3, 2020, at 3:00 p.m., to hold a public hearing to consider the proposed Ordinance (File No. 191253) ordering the vacation of the sidewalk …3 Mar 2020 · Board of Supervisors · Filed
- Approving various parking and traffic modifications along Mission Street associated with the Mission Street Excelsior Safety Project17 Sep 2019 · SFMTA Board · ADOPTED — 5 ayes
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Better Market StreetSFMTA · Current · 10 shared street segments
- Mission Street Safety Improvements ProjectPublic Works · Design · 5 shared street segments
- 1st Street Safety Improvements ProjectPublic Works · Planning · 3 shared street segments
- Active Beale StreetSFMTA · 3 shared street segments
- Various Locations Large Diameter Sewer Improvements No 1Public Works · Design · 2 shared street segments
- Battery/Sansome Quick-Build ProjectSFMTA · Completed · 2 shared street segments
- Bikeway HardeningSFMTA · Planning · 2 shared street segments
- Front Street, Sansome Street, 1st Street, and Montgomery Street Pavement Renovation and Sewer ReplacementPublic Works · Design · 2 shared street segments
How we built this: About the Data