Alemany Boulevard Infrastructure Improvements Project
0% in published scope
Public Works · Streetscape · In progress · Under way, no end date published
1 of the project's 3 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- Alemany Blvd
- Planned bikeway
- Separated bikeway, 0.67 mi on Alemany Blvd
- Scope
- “San Francisco Public Works is scheduled to repave Alemany Blvd. in the southbound direction between Santa Rosa Avenue and San Juan Avenue. The grinding (removal of existing asphalt from the roadway) and paving phase is scheduled to commence on -- During the grinding phase (removal of existing asphalt from the roadway), access to enter and exit driveways will be maintained, however slight delays should be expected if crews are working on the lane closest to your driveway. Please allow extra travel time. Sidewalks will remain open at all times. – During the paving phase, driveway access may be d”
- Dates
Start End Public consultation not published not published Construction June 2019 not published - Records
- Public Works project page
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
5 other projects on these street segments
- Excelsior Neighborhood Traffic Calming ProjectSFMTA · Completed · 17 shared street segments
- District 11-Wide Traffic Calming ProjectSFMTA · 16 shared street segments
- Alemany Corridor Safety ProjectSFMTA · Completed · 13 shared street segments
- Contract 65 New Traffic SignalsSFMTA · Legislated · 7 shared street segments
- PW As Needed Spot Sewer Replacement No 47Public Works · Construction · 1 shared street segment