Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Sewer Replacement No 36
0% in published scope
Public Works · Sewer, water or power · Design · Starts 30 Jan 2028, ends 1 Apr 2029
The project's one street segment on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 17th St, Alma St, Aquavista Way, Belvedere St, Beulah St, Bigler Ave
- Planned bikeway
- Bikeway of undecided type, 0.32 mi on Clarendon Ave
- Would reach
- 3,030 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 1,249 residents with none within about one block (440 feet) today would have one; 1,255 residents with none within about two blocks (880 feet) today would have one
- Scope
- “2689i”
- Dates
Start End Public consultation not published not published Construction Jan 2028 Apr 2029 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Sewer Upgrades: Renewal & Replacement Program
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
7 decisions on the same streets, not naming this project
- ESTABLISH – RECTANGULAR RAPID FLASHING BEACONS (RRFB) Parnassus Avenue, eastbound and westbound, at Willard Street (Supervisor District 8) (Approvable by the City Traffic Engineer) Corbin Skerrit, [staff email removed — …11 Jul 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WD-2844, 12-Inch Ductile Iron Water Main Installation on Parnassus Avenue, from Stanyan Street to 6th Avenue, on Lawton Street from 7th Avenue to Funston Avenue, and Various Street Locations, to the re…24 Sep 2024 · SFPUC Commission · approve the Consent Calendar
- Approving parking and traffic modifications along 17th Street between Potrero Avenue and Mississippi Street to improve transportation safety and connectivity5 Mar 2024 · SFMTA Board · ADOPTED — 7 ayes (Resolution 240305-020)
- Accept work performed by M Squared Construction, Inc., under Contract No. WD-2811, 8- Inch and 16-Inch Ductile Iron Water Main Replacement on 17th Street from Clayton Street to Douglass Street and Various Side Streets; a…9 Jan 2024 · SFPUC Commission · approve items 6a through 6i
- ESTABLISH – CLASS IV BIKEWAY 17th Street, eastbound and westbound, between Potrero Avenue and Mississippi Street (Approvable by the City Traffic Engineer) 4(b). ESTABLISH – STOP SIGNS 17th Street, eastbound and westbound…1 Sep 2023 · Engineering hearing · Item 4(a) corrected to reflect approvability by the City Traffic Engineer. Item 4(c) updated to TOW AWAY NO STOPPING ANY TIME as originally proposed. Items 4(a) through 4(s) approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Belvedere Street, west side, from 22 feet to 83 feet south of Haight Street (Supervisor District 5) (Approvable by the City Traffic Engineer) Laura S…2 Dec 2022 · Engineering hearing · Item put on hold at the request of the Mayor’s Office.
- ESTABLISH – SPEED TABLES 17th Street, between Market Street and Diamond Street (2 speed tables) 17(b). ESTABLISH – CROSSWALK 17th Street, midblock between Diamond Street and Castro Street 17(c). ESTABLISH – CLASS IV BIKE…18 Oct 2019 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation. Public Comments: Comments received in opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Street Resurfacing Program-BBSR Paving FY 27-28Public Works · Planning · 3 shared street segments
- Various Locations Pavement Renovation No 69Public Works · Construction · 2 shared street segments
- PW Various Locations Sewer Replacement No 18Public Works · Construction · 1 shared street segment
- Various Location Sewer Replacement No 22Public Works · Design · 1 shared street segment
- Upper Haight Transit Improvement and Pedestrian Realm ProjectPublic Works · In progress · 1 shared street segmentPublic Works' page gives its status as In progress; SFMTA's project layer gives its phase as Completed.
- Upper Haight Transit Improvement and Pedestrian Realm ProjectSFMTA · Completed · 1 shared street segment
- Twin Peaks Figure 8 Redesign ProjectSFMTA · Completed · 1 shared street segment
- Various Locations Pavement Renovation No 85Public Works · Construction · 1 shared street segment
How we built this: About the Data