252 street projects under way or coming up on the Biking and Rolling Plan's network.
Winston Drive Quick-Build Project
Builds 49%
SFMTA · Bike, walk or safety · Implementation / Construction · No start date published, ends 30 Sep 2026
4 of the project's 7 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 0.66 mi of the plan's bikeway.
- Streets
- Lake Merced Blvd, Winston Dr
- Planned bikeway
- Separated bikeway, 2.1 mi on Winston Dr, Lake Merced Blvd
Shared-use path, 0.66 mi on Lake Merced Blvd - Would reach
- 0 residents (2020 census), 1 library would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 4 street segments that lack one. Closer in: 84 residents with none within about one block (440 feet) today would have one; 204 residents, 1 library with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction not published September 2026 - Records
- SFMTA project page
City decisions naming this project
- Approving the Winston Drive Quick-Build Project to improve transportation safety and connectivity, including the conversion of existing Class II bikeways (bike lanes) to a Class IV separated bikeway on Winston Drive betw…2 Sep 2025 · SFMTA Board · ADOPTED — 6 ayes (Resolution 250902-083)
1 milestones and events from the project's own page
- Board of Directors Meeting, September 2, 20252 Sep 2025 · Project page event
3 decisions on the same streets, not naming this project
- ESTABLISH – TOW AWAY NO STOPPING ANYTIME A. Winston Drive, south side, from Lake Merced Boulevard to Buckingham Way B. Winston Drive, north side, from 198 feet to 248 feet east of Lake Merced Boulevard C. Winston Drive, …2 May 2025 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Approve and recommend to the Board of Supervisors the conditional termination of certain sewer and water easements encumbering San Francisco Blocks 7332, 7333, 7333A, and 7333B located within Parkmerced near Lake Merced …24 May 2022 · SFPUC Commission · approve Item 14
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 230 Buckingham Way, east side, from 247 feet to 322 feet south of the midblock crosswalk at 270 Buckingham Way (75-foot bike share station in the par…5 Nov 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.
5 other projects on these street segments
- Holloway Ave and Lake Merced Blvd Pavement RenovationPublic Works · Planning · 5 shared street segments
- Lake Merced Quick-Build ProjectSFMTA · Completed · 3 shared street segments
- PEFWS Pipeline - 36- & 42-inch Welded Steel PipeSFPUC · Design · 2 shared street segments
- Various Locations Sewer Replacement No 38Public Works · Design · 1 shared street segment
- PW FS 19 Emergency Generator ReplacementPublic Works · Construction · 1 shared street segment
1 documents on the project page