SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Western Addition Community Safe Streets

Not stated

SFMTA · Bike, walk or safety · Detailed Design · Starts Winter 2027; Spring 2027 - Fall 2028, ends 30 Nov 2028

Early enough to change: SFMTA gives its phase as Detailed Design; its project page may list a contact. No meeting on it is posted for the next 60 days.

All 3 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA lists it as a bike project, but does not say whether it builds that bikeway.

Streets
Webster St
Planned bikeway
Shared street, 0.2 mi on Webster St
Would reach
No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 3 street segments that lack one. Closer in: 803 residents (2020 census), 1 school with none within about one block (440 feet) today would have one; 0 residents, 1 school with none within about two blocks (880 feet) today would have one
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJan 2027Nov 2028
Records
SFMTA project page

City decisions naming this project

4 milestones and events from the project's own page

Construction on these street segments

20262027202820292030203120322033todayWestern Addition Community Safe Stre…Various Locations Pavement Renovatio…Various Locations Pavement Renovatio…PW Various Locations Sewer Replaceme…Joint - MTA Lead - Fillmore St Pavem…Various Locations Pavement Renovation No 81 and Sewer Replacement: construction 12 Jan 2026 to 31 Aug 2027Various Locations Pavement Renovation No 85: construction Jul 2026 to 31 May 2027PW Various Locations Sewer Replacement No 19: construction 3 Mar 2027 to 1 May 2028Joint - MTA Lead - Fillmore St Pavement Renovation: construction 1 Sep 2031 to 13 Nov 2032Western Addition Community Safe Streets: construction Jan 2027 to 30 Nov 2028Jan 2027 – 30 Nov 202812 Jan 2026 – 31 Aug 2027Jul 2026 – 31 May 20273 Mar 2027 – 1 May 20281 Sep 2031 – 13 Nov 2032

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.