Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Pavement Renovation No 77
0% in published scope
Public Works · Repaving · Construction · Under way, ends 31 Aug 2027
All 16 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 12th Ave, 18th Ave, 38th Ave, Ardenwood Way, Ashwood Ln, Avon Way
- Planned bikeway
- Shared street, 0.85 mi on Taraval St, Santa Clara Ave, Laguna Honda Blvd
Separated bikeway, 0.61 mi on Sloat Blvd, Mercedes Way
Level 3 shared street, 0.064 mi on Foerster St - Would reach
- 5,844 residents (2020 census), 1 school, 2 libraries would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 16 street segments that lack one. Closer in: 4,447 residents, 3 schools with none within about one block (440 feet) today would have one; 5,551 residents, 2 schools, 1 library with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Jun 2026 August 2027 - Sources disagree
- The coordination feed gives construction ending 2027-06-14; Public Works' project page (Completion “Summer, 2027”; text “August 2027”), 2027-08-31, which is shown.
- Records
- Public Works project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Various Locations Pavement Renovation No. 77 and Sewer Replacement – Contract Award26 Feb 2026 · Public Works Commission
8 decisions on the same streets, not naming this project
- Approve an increase of 115 calendar days to the contract duration contingency for Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and, Wawona Streets, and Sloat Blvd Sewer Replacement, with Precision Engineering, Inc…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- Approve the plans and specifications and award Contract No. WW-684, 45th, 46th, 47th Aves, Vicente, Wawona Streets and Sloat Blvd. Sewer Replacement, in the amount of $7,342,613, and with a duration of 375 consecutive ca…8 Nov 2022 · SFPUC Commission · approve the Consent Calendar, with the amendment to the date on the
- Authorize the General Manager to execute a Memorandum of Understanding (MOU) with the San Francisco Municipal Transportation Agency (SFMTA) to set forth the agencies’ respective responsibilities, including cost sharing a…8 Feb 2022 · SFPUC Commission · approve Item 13
- Accept work performed by JDB & Sons Construction for Contract No. WW-611, Cutler Avenue, Lower Great Highway, Sloat Boulevard, and Wawona Street Sewer Replacement; approve Modification No. 6 (Final) decreasing the contra…23 Nov 2021 · SFPUC Commission · approve Consent Calendar items 10a, 10c, 10d, and 10e
- Approve an increase of 280 calendar days to the contract duration contingency for Contract No. WW-691, Sunset Boulevard Greenway – Phase II, Irving Street to Ulloa Street with Minerva Construction, Inc.; and authorize th…27 Apr 2021 · SFPUC Commission · approve Consent Calendar items 9a and 9b
- Authorize the General Manager to execute a Project Partnership Agreement with the Army Corps of Engineers (ACOE) for the construction of the Ocean Beach Beneficial Use of Dredged Materials Project to place sand dredged f…23 Feb 2021 · SFPUC Commission · approve Consent Item 22
- ESTABLISH – SIDEWALK BIKE SHARE STATION 38th Avenue, west side, from 12 feet to 79 feet south of Balboa Street (67-foot bike share station) (Supervisor District 1) Project Contact: Laura Stonehill, [staff email removed —…12 Jun 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 18th Avenue, west side, from 241 feet to 310 feet north of California Street (62-foot bike share station with red zones on either side) (Supervisor D…21 Feb 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
7 other projects on these street segments
- PW Various Locations Sewer Replacement (JV VL PR No 77)Public Works · Construction · 8 shared street segments
- 19th Ave & Lawton Stother · Planning · 3 shared street segments
- Frida Kahlo Way Quick-Build ProjectSFMTA · Legislated · 2 shared street segments
- PW Various Locations Sewer Replacement (JV VL PR No 69)Public Works · Construction · 1 shared street segment
- Outer Sunset Traffic Management ProjectSFMTA · Completed · 1 shared street segment
- Vicente Street Bicycle and Pedestrian Safety ProjectSFMTA · Completed · 1 shared street segment
- Various Locations Sewer Replacement No 27Public Works · Design · 1 shared street segment
How we built this: About the Data