Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

WD-2918 8-Inch Ductile Iron Water Main Replacement, Sewer Rehabilitation and Sewer Replacement on Harkness Ave., Goettingen St., Girard St., and Various Locations

0% in published scope

SFPUC · Sewer, water or power · Design · Under way, ends 16 Feb 2029

All 5 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
Alder St, Ankeny St, Bishop St, Brussels St, Campbell Ave, Delta St
Planned bikeway
Separated bikeway, 0.27 mi on Mansell St
Shared street, 0.056 mi on Girard St
Would reach
212 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 5 street segments that lack one. Closer in: 1,123 residents, 1 school with none within about one block (440 feet) today would have one; 978 residents, 2 schools with none within about two blocks (880 feet) today would have one
Scope
“8-inch Ductile Iron Water Main Replacement on Goettingen, Brussels, Giard and Harkness Streets”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJul 2026Feb 2029
Sources disagree
The start date has passed (2026-07-13) while the phase is still Design, per the coordination feed.
Records
Interagency coordination feed record (DataSF row) · No SFPUC page for this job; closest official source: Water Main Replacement Process

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

Construction on these street segments

201920212023202520272029203120332035todayWD-2918 8-Inch Ductile Iron Water Ma…San Bruno Ave Multimodal Improvement…Visitacion Valley and Portola Commun…PW StreetResurfacingPro-BBSR Pavemen…8-Inch Ductile Iron Water Main Repla…Various Locations Sewer Replacement …Various Locations Sewer Replacement …Various Locations Pavement Renovatio…PW StreetResurfacingPro-BBSR Pavement Prese FY 26-27: construction 1 Jul 2026 to 7 Jul 20278-Inch Ductile Iron Water Main Replacement on Harkness, Goettingen, Brussels, Girard Streets and Various Streets: construction 1 Sep 2026 to 31 Aug 2027Various Locations Sewer Replacement No 25: construction 25 Feb 2027 to 31 Mar 2028Various Locations Sewer Replacement No 34: construction 1 Jun 2028 to 31 May 2029Various Locations Pavement Renovation Concrete No 97: construction 28 Feb 2034 to 14 May 2035San Bruno Ave Multimodal Improvement Project: construction 2019 to end not publishedVisitacion Valley and Portola Community Based Transportation Plan: construction start not published to 31 May 2023WD-2918 8-Inch Ductile Iron Water Main Replacement, Sewer Rehabilitation and Sewer Replacement on Harkness Ave., Goettingen St., Girard St., and Various Locations: construction 13 Jul 2026 to 16 Feb 202913 Jul 2026 – 16 Feb 2029from 2019until 31 May 20231 Jul 2026 – 7 Jul 20271 Sep 2026 – 31 Aug 202725 Feb 2027 – 31 Mar 20281 Jun 2028 – 31 May 202928 Feb 2034 – 14 May 2035

Construction start and end as each department publishes them; a dot where only one is published. 1 other project on these street segments publishes no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.