Stormwater Trash Capture

0% in published scope

Public Works · Spot repairs · Design · Starts 28 Jun 2027, ends 24 Mar 2028

Early enough to change: Public Works gives its phase as Design. No meeting on it is posted for the next 60 days.

4 of the project's 8 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
26th St, Amador St, Cargo Way, Chestnut St, Error, Folsom St
Planned bikeway
Separated bikeway, 2.3 mi on The Embarcadero
Scope
“2492i_Installation of high flow trash capture systems at 7 sites within Port Jurisdiction with the objective to reduce trash discharges into San Francisco Bay Waters.”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJun 2027Mar 2028
Official source
No Public Works page for this job, and no closest official source found: Public Works' site search for “trash capture” returned no page, and SFPUC's Sewer System Upgrades Improvement Program page does not name trash capture; the job is in Port jurisdiction (2026-09-29).
Records
Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

10 decisions on the same streets, not naming this project

Construction on these street segments

2023202420252026202720282029todayStormwater Trash CaptureNorthern Waterfront Electrical Impro…Central Embarcadero Safety ProjectTransbay Howard Streetscape Improvem…Stormwater Trash Capture Phase 2Northern Waterfront Electrical Improvements (NWEI): construction 1 Apr 2023 to 31 Dec 2026Central Embarcadero Safety Project: construction 2026 to 31 Dec 2028Transbay Howard Streetscape Improvement Project: construction 2026 to 31 Dec 2028Stormwater Trash Capture Phase 2: construction 29 Nov 2027 to 29 Jul 2028Stormwater Trash Capture: construction 28 Jun 2027 to 24 Mar 20281 Apr 2023 – 31 Dec 202628 Jun 2027 – 24 Mar 20282026 – 31 Dec 20282026 – 31 Dec 202829 Nov 2027 – 29 Jul 2028

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.