Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Bayview Community Based Transportation Plan

Not stated

SFMTA · Bike, walk or safety · Planning · Under way, no end date published

103 of the project's 130 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA lists it as a bike project, but does not say whether it builds that bikeway.

Streets
Evans Ave, Bay Shore Blvd, Cargo Way, Oakdale Ave, Mendell St, Carroll Ave
Planned bikeway
Separated bikeway, 11 mi on Evans Ave, Bay Shore Blvd, Cargo Way, Innes Ave
Shared street, 10 mi on Oakdale Ave, Mendell St, Carroll Ave, Quesada Ave
Shared-use path, 0.13 mi on Yosemite Ave
Scope
None published.
Dates
StartEnd
Public consultationSummer 20182021-04-22 – 2021-05-13
Construction2022not published
Sources disagree
The project page's timeline and event cards give the latest public consultation as 2021-05-13; the page's text gives 2021-09 (“September of 2021”).
Public Works' page gives its status as In progress; SFMTA's project layer gives Planning.
The start date has passed (2022) while the phase is still Planning, per SFMTA's project layer.
Records
SFMTA project page · Public Works project page (Bayview Transportation Improvements Project)

City decisions naming this project

1 earlier
7 milestones and events from the project's own page
20 decisions on the same streets, not naming this project

Construction on these street segments

20222023202420252026202720282029203020312032todayBayview Community Based Transportati…Visitacion Valley and Portola Commun…WD-2921 8- and 12-inch Ductile Iron …Bayview Multimodal ProjectWD-2937 2425-003: 8-inch Ductile Iro…Bayview Community PathwayVarious Locations Pavement Renovatio…WD-2921 8- and 12-inch Ductile Iron Water Main Replacement on Palou, Quesada, and Revere Ave from 3rd St to Griffith St: construction 1 Apr 2026 to 1 Apr 2028Bayview Multimodal Project: construction 30 Jun 2027 to 31 Dec 2028WD-2937 2425-003: 8-inch Ductile Iron Water Main Replacement on Underwood, Thomas, and Shafter Aves from 3rd St to Griffith St: construction 4 Aug 2027 to 4 Aug 2029Bayview Community Pathway: construction 2028 to 31 Dec 2028Various Locations Pavement Renovation No 100: construction 29 Apr 2030 to 12 Jul 2031Visitacion Valley and Portola Community Based Transportation Plan: construction start not published to 31 May 2023Bayview Community Based Transportation Plan: construction 2022 to end not publishedfrom 2022until 31 May 20231 Apr 2026 – 1 Apr 20282028 – 31 Dec 202830 Jun 2027 – 31 Dec 20284 Aug 2027 – 4 Aug 202929 Apr 2030 – 12 Jul 2031

Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.

8 other projects on these street segments
19 documents on the project page