Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Bayview Community Based Transportation Plan
Not stated
SFMTA · Bike, walk or safety · Planning · Under way, no end date published
103 of the project's 130 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA lists it as a bike project, but does not say whether it builds that bikeway.
- Streets
- Evans Ave, Bay Shore Blvd, Cargo Way, Oakdale Ave, Mendell St, Carroll Ave
- Planned bikeway
- Separated bikeway, 11 mi on Evans Ave, Bay Shore Blvd, Cargo Way, Innes Ave
Shared street, 10 mi on Oakdale Ave, Mendell St, Carroll Ave, Quesada Ave
Shared-use path, 0.13 mi on Yosemite Ave - Scope
- None published.
- Dates
Start End Public consultation Summer 2018 2021-04-22 – 2021-05-13 Construction 2022 not published - Sources disagree
- The project page's timeline and event cards give the latest public consultation as 2021-05-13; the page's text gives 2021-09 (“September of 2021”).
Public Works' page gives its status as In progress; SFMTA's project layer gives Planning.
The start date has passed (2022) while the phase is still Planning, per SFMTA's project layer. - Records
- SFMTA project page · Public Works project page (Bayview Transportation Improvements Project)
City decisions naming this project
- ESTABLISH – RECTANGULAR RAPID FLASHING BEACON (RRFB) Williams Avenue at Apollo Street Innes Avenue at Arelious Walker Drive (Supervisor District 10) (Approvable by the City Traffic Engineer) Daniel Carr, [staff email rem…3 Apr 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Adopting the Bayview Community Based Transportation Plan18 Feb 2020 · SFMTA Board · ADOPTED — 7 ayes
- Approve the Participatory Budgeting Program of Projects Identified Through the Bayview Community Based Transportation Plan Process17 Dec 2019 · SFCTA Board
- Approve the Participatory Budgeting Program of Projects Identified Through the Bayview Community Based Transportation Plan Process10 Dec 2019 · SFCTA Board
- ESTABLISH – SPEED HUMPS Quesada Avenue, between Keith Street and Lane Street (2 speed humps) (Supervisor District 10) Ariel Ward, [staff email removed — see the order] This proactive traffic calming measure was developed…6 Dec 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: No comments received.
1 earlier
- ESTABLISH – SPEED HUMPS Quesada Avenue, between Jennings Street and Ingalls Street (2 speed humps) (Supervisor District 10) Ariel Ward, [staff email removed — see the order] This proactive traffic calming measure was dev…6 Dec 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: No comments received.
7 milestones and events from the project's own page
- Virtual Open House for the Williams Avenue Quick-Build Safety Project22 Apr 2021 · Project page event
- Virtual Open House for the Bayview Quick Build Project7 Sep 2020 · Project page event
- Board of Directors meeting, February 18, 202018 Feb 2020 · Project page event
- Plan AdoptionWinter 2020 · Project page timeline · Pending
- Plan DevelopmentSummer 2019 · Project page timeline · Pending
- Community EngagementSummer 2018 · Project page timeline · Pending
- Plan Review & StudySpring 2018 · Project page timeline · Pending
20 decisions on the same streets, not naming this project
- ESTABLISH – CLASS IV BIKEWAY Bayshore Boulevard, east side, southbound, between Jerrold Avenue and Marin Street (two-way protected bikeway) (Supervisor District 10) (Approvable by the City Traffic Engineer) Brian Donahoe…5 Dec 2025 · Engineering hearing · Revised approval path. Approved by the City Traffic Engineer for implementation.
- ESTABLISH – TOW–AWAY, NO PARKING ANY TIME A. Evans Avenue, south side, from Rankin Street to 193 feet easterly (removes 7 unmetered parking spaces in the vicinity of rail crossing) B. Evans Avenue, south side, from 483 f…14 Nov 2025 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Award Contract No. WW-790, Evans Ave. and Mariposa St. Outfalls Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $2,576,348, with a duration of 379 con…9 Sep 2025 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. WW-757R, Laguna, Howard, and Mission Creek Combined Sewer Discharge Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $7,296,786, wit…13 May 2025 · SFPUC Commission · approve the Consent Calendar
- Approve an increase of 368 calendar days (approximately one year) to the duration contingency for Design Build Contract No. DB-130, Bay Corridor Transmission and Distribution (BCTD) – Phase 3 (2019), with Beta Engineerin…13 Aug 2024 · SFPUC Commission
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Toland Street, east side, from 12 feet to 48 feet south of Jerrold Avenue (36-foot bike share station) (Supervisor District 10) (Approvable by the C…3 May 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approving bicycle, parking and traffic modifications along Bayshore Boulevard and Cesar Chavez Street associated with the Cesar Chavez/Bayshore Boulevard/U.S. 101 Project16 Jan 2024 · SFMTA Board · ADOPTED — 6 ayes (Resolution 240116-006)
- ESTABLISH – CLASS IV BIKEWAY (PARKING PROTECTED BIKEWAY) Bayshore Boulevard, northbound and southbound, between Silver Avenue and Oakdale Avenue 13(b). ESTABLISH – TRANSIT BOARDING ISLAND Bayshore Boulevard, east side, f…17 Mar 2023 · Engineering hearing
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Hudson Avenue, north side, from 3rd Street to 52 feet westerly (Supervisor District 10) (Approvable by the City Traffic Engineer) Laura Stonehill, [s…17 Feb 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of 180 consecutive calendar days to the contract duration contingency for Contract No. WW-696, Cargo Way Flush Line, with JMB Construction, Inc.; and authorize the General Manager to approve future mo…14 Dec 2021 · SFPUC Commission · approve Consent Calendar items 10a through 10g
- ESTABLISH - NO PARKING ANYTIME EXCEPT BICYCLES 3rd Street, east side, from 390 feet to 420 feet north of 23rd Street (Supervisor District 10) (Approvable by the City Traffic Engineer) Pallavi Panyam, [staff email removed…4 Jun 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- Approve an increase of 96 calendar days to the contract duration contingency for Contract No. WW-696, Cargo Way Flush Line; and authorize the General Manager to approve future modifications to the contract for a total co…9 Mar 2021 · SFPUC Commission · approve Consent items 9c, d, f, and h
- ESTABLISH – CLASS IV BIKEWAY A. Evans Avenue, south side, from Keith Street to Jennings Street B. Evan Avenue, both directions, from Jennings Street to Hunters Pt. Boulevard C. Hunters Point Boulevard, both directions, f…4 Dec 2020 · Engineering hearing · Items 10(b) withdrawn due to San Francisco Fire Department concerns. The remaining items to be approved by the City Traffic Engineer for implementation after receipt of environmental clearance.
- ESTABLISH – TRAFFIC SIGNAL Oakdale Avenue and Loomis Street 3(b). ESTABLISH – NO TURN ON RED Oakdale Avenue, westbound, at Loomis Street 3(c). ESTABLISH – PERPENDICULAR PARKING Loomis Street, east side, from 10 feet nort…4 Sep 2020 · Engineering hearing · Approved by the City Traffic Engineer to send to the SFMTA Board for approval and implementation. Sustainable Streets Division
- RESCIND - GENERAL METER PARKING, 1-HOUR TIME LIMIT, 9 AM TO 6 PM, MONDAY THROUGH SATURDAY 3rd St, west side, from 82 feet south to 102 feet south of Bayview Ave Sustainable Streets Division 10(b). ESTABLISH - NO PARKING …12 Jun 2020 · Engineering hearing · On hold pending further community outreach. Public Comments: Comments received in support and opposition.
- ESTABLISH – SIDEWALK BIKE SHARE STATION Egbert Avenue, north side, from Jennings Street to 72 feet easterly (70-foot bike share station) (Supervisor District 10) Laura Stonehill, [staff email removed — see the order] Pro…1 Nov 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
- Ordinance ordering the street vacation of the entirety of Seawall Lot 337 (located east of Third Street between China Basin Channel and Mission Rock Street, including China Basin Park) and portions of Terry A. Francois B…10 Sep 2019 · Board of Supervisors · Passed
- Hearing of the Board of Supervisors sitting as a Committee of the Whole on September 3, 2019, at 3:00 p.m., to hold a public hearing to consider the proposed Ordinance (File No. 190654) ordering the street vacation of th…3 Sep 2019 · Board of Supervisors · Filed
- Resolution declaring the intent of the Board of Supervisors to order the street vacation for the entirety of Seawall Lot 337 (located east of Third Street between China Basin Channel and Mission Rock Street, including Ch…16 Jul 2019 · Board of Supervisors · Passed
- Ordinance ordering the street vacation of a portion of Hudson Avenue, adjacent to Assessor’s Parcel Block No. 4629A, Lot Nos. 010 and 011, and Assessor’s Parcel Block No. 4646, Lot No. 022, and a portion of Hunters Point…Undated · Board of Supervisors · Pending Committee Action
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Candlestick Point/Hunters Point ShipyardSFMTA · Planning · 60 shared street segments
- Bayview Multimodal ProjectPublic Works · Design · 50 shared street segments
- Bayview Community PathwaySFMTA · Planning · 35 shared street segments
- Visitacion Valley and Portola Community Based Transportation PlanSFMTA · Planning · 33 shared street segments
- WD-2921 8- and 12-inch Ductile Iron Water Main Replacement on Palou, Quesada, and Revere Ave from 3rd St to Griffith StSFPUC · Construction · 31 shared street segments
- 3rd St from Mariposa St to Palou Ave Pavement RenovationPublic Works · Planning · 31 shared street segments
- WD-2937 2425-003: 8-inch Ductile Iron Water Main Replacement on Underwood, Thomas, and Shafter Aves from 3rd St to Griffith StSFPUC · Design · 31 shared street segments
- Various Locations Pavement Renovation No 100Public Works · Planning · 23 shared street segments
19 documents on the project page
- Williams Quick-Build Virtual Open House - Comments Received
- SFCTA District 10 Mobility Management Study 2018
- Bayview Bulb-Outs Fact Sheet
- Bayview CBTP Final Plan
- Bayview CBTP Board Presentation
- Bayview CBTP Draft Plan
- Bayview CBTP Phase 3 Outreach Report & Streetscape Plan
- Bayview CBTP Public Ballot Materials
- Bayview CBTP Phase 2 outreach recap
- Bayview CBTP Phase 2 Workshop Materials
- Bayview CBTP Participatory Budgeting Information
- Bayview CBTP Statement of Intent
- Bayview CBTP Phase 1 outreach recap
- Bayview CBTP Phase 1 Workshop
- Bayview CBTP Plan Review
- Bayview CBTP Fact Sheet - English
- Bayview CBTP Fact Sheet - Chinese
- Bayview CBTP Fact Sheet - Spanish
- SFCTA Bayview-Hunters Point Neighborhood Transportation Plan 2010
How we built this: About the Data