Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations
Already built
SFPUC · Sewer, water or power · Design · Starts 23 Feb 2027, ends 25 Feb 2028
The project's one street segment on a planned bikeway street already has an all-ages bikeway.
- Streets
- 47th Ave, Cabrillo St, John F Kennedy Dr
- Planned bikeway
- Car-free street, 0.43 mi on Martin Luther King Jr Dr
- Scope
- “12-Inch Cast Iron Water Main Rehabilitation on 45th Ave. from Lincoln Way to Martin Luther King Jr. Dr., on 47th Ave. from John F. Kennedy Dr. to Cabrillo St., and on Various Street Locations”
- Dates
Start End Public consultation not published not published Construction Feb 2027 Feb 2028 - Records
- Interagency coordination feed record (DataSF row) · No SFPUC page for this job; closest official source: Water Main Replacement Process
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
6 decisions on the same streets, not naming this project
- Approve an increase of 115 calendar days to the contract duration contingency for Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and, Wawona Streets, and Sloat Blvd Sewer Replacement, with Precision Engineering, Inc…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- ESTABLISH – STOP Signs Cabrillo Street, eastbound and westbound, at 2nd Avenue (Supervisor District 1) (Approvable by the City Traffic Engineer) Edward Tang, [staff email removed — see the order]2 Jun 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 45th Avenue, east side, from Noriega Street to 64 feet southerly (53-foot bike share station with red zones on each side of the station) (Supervisor …6 Jan 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve the plans and specifications and award Contract No. WW-684, 45th, 46th, 47th Aves, Vicente, Wawona Streets and Sloat Blvd. Sewer Replacement, in the amount of $7,342,613, and with a duration of 375 consecutive ca…8 Nov 2022 · SFPUC Commission · approve the Consent Calendar, with the amendment to the date on the
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 45th Avenue, east side, from Noriega Street to 64 feet southerly (53-foot bike share station with red zones on each side of the station) (Supervisor …18 Feb 2022 · Engineering hearing · Item withdrawn.
- Accept work performed by Marinship Development Interest, LLC, for Contract No. WW-694, Lincoln Way/48th Ave Diversion Structure Modification; approve Modification No. 1 (Final), decreasing the contract amount by $7,400, …9 Feb 2021 · SFPUC Commission · approve Consent Calendar items 9a through 9d
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 1 other project on these street segments publishes no construction dates.
2 other projects on these street segments
- Golden Gate Park Access and Safety ProgramSFMTA · Legislated · 1 shared street segment
- Golden Gate Park Traffic Safety ProjectSFMTA · Completed · 1 shared street segment