Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Contract 66 New Traffic Signals

Not stated

SFMTA with Public Works · Bike, walk or safety · Detailed Design · Starts Fall 2027 - Fall 2028, ends 30 Nov 2028

Early enough to change: SFMTA gives its phase as Detailed Design; its project page may list a contact. No meeting on it is posted for the next 60 days.

8 of the project's 13 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA lists it as a bike project, but does not say whether it builds that bikeway.

Streets
Great Hwy, 4th St, 41st Ave, Guerrero St, San Jose Ave, Martin Luther King Jr Dr
Planned bikeway
Shared-use path, 6 mi on Great Hwy
Separated bikeway, 3.1 mi on Great Hwy, Guerrero St, San Jose Ave
Bikeway of undecided type, 0.34 mi on 4th St
Shared street, 0.26 mi on 41st Ave
Car-free street, 0.17 mi on Martin Luther King Jr Dr
Would reach
No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 8 street segments that lack one. Closer in: 1,622 residents (2020 census), 1 school with none within about one block (440 feet) today would have one
Scope
“Contract 66 will install new traffic signals at (12) locations. All new signal locations will have new pedestrian countdown signals (PCS), accessible pedestrian signals (APS), controllers, conduit, wiring, poles, and curb ramps. The (12) locations that will receive traffic signals are 10th Avenue\Lincoln, 39th Avenue\Fulton, 28th Street\Guerrero, 41st Avenue\Lincoln, 4th Street\Long Bridge, 4th Street\Mission Rock, 4th Avenue\Fulton, Mission\Mary\Mint, Cesar Chavez\Florida, Divisadero\Castro\Wal”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionFall 2027 - Fall 2028Nov 2028
Sources disagree
The coordination feed gives construction starting 2027-03-01; SFMTA's project page gives 2027-10, which is shown.
The coordination feed gives construction ending 2028-03-01; SFMTA's project page gives 2028-11-30, which is shown.
The coordination feed gives construction starting 2027-07-01; SFMTA's project page gives 2027-10, which is shown.
The coordination feed gives construction ending 2029-01-10; SFMTA's project page gives 2028-11-30, which is shown.
SFMTA gives the phase as Detailed Design; the coordination feed gives Design.
Records
SFMTA project page · Interagency coordination feed record (DataSF row) · Interagency coordination feed record (DataSF row)

City decisions naming this project

5 earlier
6 milestones and events from the project's own page
19 decisions on the same streets, not naming this project

Construction on these street segments

202520262027202820292030todayContract 66 New Traffic SignalsGolden Gate Park Access and Safety P…WD-2922: 8-inch Ductile Iron Water M…Golden Gate Park Access and Safety Program: construction 1 Feb 2025 to 31 Dec 2028WD-2922: 8-inch Ductile Iron Water Main Replacement on Lincoln Way from Sunset to La Playa St and Various Side Streets: construction 25 Jun 2028 to 6 Nov 2029Contract 66 New Traffic Signals: construction Oct 2027 to 30 Nov 2028Oct 2027 – 30 Nov 202825 Jun 2028 – 6 Nov 20291 Feb 2025 – 31 Dec 2028

Construction start and end as each department publishes them; a dot where only one is published. 6 other projects on these street segments publish no construction dates.

8 other projects on these street segments
1 documents on the project page