Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

12th Avenue Slow Street

Builds 100%

SFMTA · Bike, walk or safety · Legislated · Under way, no end date published

All 4 of the project's street segments on planned bikeway streets already have an all-ages bikeway.

Streets
12th Ave
Planned bikeway
Shared street, 1 mi on 12th Ave
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
Construction2021not published
Records
SFMTA project page

City decisions naming this project

4 decisions on the same streets, not naming this project

Construction on these street segments

2021202220232024202520262027202820292030today12th Avenue Slow StreetVarious Locations Sewer Replacement …Various Locations Sewer Replacement …Various Locations Sewer Replacement No 30: construction 12 Apr 2027 to 19 Jul 2028Various Locations Sewer Replacement No 37: construction 3 May 2028 to 2 Nov 202912th Avenue Slow Street: construction 2021 to end not publishedfrom 202112 Apr 2027 – 19 Jul 20283 May 2028 – 2 Nov 2029

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

6 other projects on these street segments
1 documents on the project page