Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

PW Various Locations Sewer Replacement (JV VL PR No 69)

0% in published scope

Public Works · Sewer, water or power · Construction · Under way, ends 12 Oct 2027

All 5 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
Balceta Ave, Claremont Blvd, Clarendon Ave, Hernandez Ave, Juanita Way, Laguna Honda Blvd
Planned bikeway
Bikeway of undecided type, 0.57 mi on Clarendon Ave
Shared street, 0.27 mi on Laguna Honda Blvd
Would reach
2,271 residents (2020 census), 2 schools would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 5 street segments that lack one. Closer in: 2,608 residents with none within about one block (440 feet) today would have one; 2,046 residents, 2 schools with none within about two blocks (880 feet) today would have one
Scope
“2297i”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionFall, 2025Oct 2027
Sources disagree
The coordination feed gives construction starting 2025-08-18; Public Works' project page (Start “Fall, 2025”; text “Fall, 2025”), 2025-10, which is shown.
The coordination feed gives construction ending 2027-10-12, which is shown; Public Works' project page (Completion “Winter, 2026”; text “Winter, 2026”) gives 2026-02-28, an end that has passed while the page still gives the job as not completed.
Records
Public Works project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

1 decisions on the same streets, not naming this project

Construction on these street segments

202520262027202820292030todayPW Various Locations Sewer Replaceme…Various Locations Pavement Renovatio…Various Locations Pavement Renovatio…Various Locations Sewer Replacement …Various Locations Pavement Renovation No 69: construction Oct 2025 to 12 Oct 2027Various Locations Pavement Renovation No 77: construction 15 Jun 2026 to 31 Aug 2027Various Locations Sewer Replacement No 37: construction 3 May 2028 to 2 Nov 2029PW Various Locations Sewer Replacement (JV VL PR No 69): construction Oct 2025 to 12 Oct 2027Oct 2025 – 12 Oct 2027Oct 2025 – 12 Oct 202715 Jun 2026 – 31 Aug 20273 May 2028 – 2 Nov 2029

Construction start and end as each department publishes them; a dot where only one is published.

3 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.