Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Pavement Renovation No 87
Already built
Public Works · Repaving · Design · Starts 13 Mar 2027, ends 26 May 2028
All 3 of the project's street segments on planned bikeway streets already have an all-ages bikeway.
- Streets
- 14th St, 6th St, Alameda St, Brosnan St, Bryant St, Clinton Park
- Planned bikeway
- Separated bikeway, 0.24 mi on Valencia St
- Scope
- “2438I”
- Dates
Start End Public consultation not published not published Construction Mar 2027 May 2028 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
6 decisions on the same streets, not naming this project
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES 14th Street, north side, from 37 feet to 53 feet east of Woodward Street (for 16-foot corral) 12(b). RESCIND – RED ZONE 14th Street, north side, from Woodward Street to 10…4 Sep 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WW-757R, Laguna, Howard, and Mission Creek Combined Sewer Discharge Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $7,296,786, wit…13 May 2025 · SFPUC Commission · approve the Consent Calendar
- Approve an increase of 365 calendar days to the contract duration contingency for Contract No. WW-697, As-Needed Main Sewer Replacement No. 8, with JDB & Sons Construction, Inc.; and authorize the General Manager to appr…24 Jan 2023 · SFPUC Commission · approve Consent Calendar Items 8a through 8c
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Harrison Street, west side, from 9 feet to 66 feet north of 14th Street (Supervisor District 9) (Approvable by the City Traffic Engineer) Laura Stone…21 Oct 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve the plans and specifications, and award Contract No. WW-712, New Montgomery, Jessie, Minna, and Mission Streets Brick Sewer Rehabilitation, in the amount of $4,888,750, and with a duration of 390 consecutive cale…11 May 2021 · SFPUC Commission · approve Consent Calendar items 8c, 8d, and 8g
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Alameda Street, south side, from Henry Adams Street to 81 feet westerly (72-foot bike share station with red zones on either side) (Supervisor Distri…21 Feb 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Request made for alternate location.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- FASIP - Western SOMA and Northern Mission District Sewer SystemSFPUC · Design · 6 shared street segments
- Western SOMA and Northern Mission Districts Sewer Replacement WW-719DPublic Works · Design · 5 shared street segments
- PW Various Locations Sewer Replacement No 18Public Works · Construction · 5 shared street segments
- PW Various Locations Sewer Replacement (JV VL PR No 87)Public Works · Design · 5 shared street segments
- Folsom-Howard Streetscape ProjectSFMTA · Current · 3 shared street segments
- PW FOLSOM AREA STORMWATER IMPROVEMENT PROJECTPublic Works · Design · 2 shared street segments