SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Main Street Streetscape Project

0%: its bikeway is off the plan SFMTA's page names its bikeway on blocks off the plan's network, and none of the plan's blocks this project covers.

SFMTA with Public Works · Bike, walk or safety · Detailed Design · Under way, ends 31 Dec 2027

2 of the project's 4 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 0 mi of the plan's bikeway.

Streets
Folsom St, Market St
Planned bikeway
Separated bikeway, 0.27 mi on Folsom St
Shared street, 0.21 mi on Market St
Scope
“Transit, sidewalk, roadway, cycle track, and signal improvmements on Main street from Market Street to Folsom Street as part of the Transit Center Soda program.”
Dates
StartEnd
Public consultation2017-20192017-2019
ConstructionOct 2025Dec 2027
Sources disagree
SFMTA's project page gives construction starting 2025, a stage it still marks Pending; the coordination feed gives 2025-10-17, which is shown.
The coordination feed gives construction ending 2027-06-04; SFMTA's project page gives 2027-12-31, which is shown.
The start date has passed (2025-10-17) while the phase is still Detailed Design, per SFMTA's project layer.
SFMTA gives the phase as Detailed Design; the coordination feed gives Design.
Records
SFMTA project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

6 milestones and events from the project's own page
19 decisions on the same streets, not naming this project

Construction on these street segments

2023202420252026202720282029todayMain Street Streetscape ProjectBetter Market StreetNorthern Waterfront Electrical Impro…PW Various Locations Sewer Replaceme…Transbay Howard Streetscape Improvem…Better Market Street: construction Jan 2023 to 30 Apr 2025Northern Waterfront Electrical Improvements (NWEI): construction 1 Apr 2023 to 31 Dec 2026PW Various Locations Sewer Replacement No 17: construction 14 Nov 2024 to 15 Nov 2026Transbay Howard Streetscape Improvement Project: construction 2026 to 31 Dec 2028Main Street Streetscape Project: construction 17 Oct 2025 to 31 Dec 2027Jan 2023 – 30 Apr 20251 Apr 2023 – 31 Dec 202614 Nov 2024 – 15 Nov 202617 Oct 2025 – 31 Dec 20272026 – 31 Dec 2028

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

8 other projects on these street segments
1 documents on the project page

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.