SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Various Locations Pavement Renovation No 86B

Already built

Public Works · Repaving · Planning · Starts 30 Oct 2030, ends 12 Jan 2032

Early enough to change: Public Works gives its phase as Planning; its project page may list a contact. No meeting on it is posted for the next 60 days.

All 2 of the project's street segments on planned bikeway streets already have an all-ages bikeway.

Streets
Bay St, Beach St, Card Aly, Edgardo Pl, Edith St, Fisher Aly
Planned bikeway
Separated bikeway, 0.36 mi on Beach St
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
ConstructionOct 2030Jan 2032
Records
Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

6 decisions on the same streets, not naming this project

Construction on these street segments

20232024202520262027202820292030203120322033todayVarious Locations Pavement Renovatio…PW Various Locations Sewer Replaceme…Beach Street Quick-Build ProjectPW StreetResurfacingPro-BBSR Pavemen…Various Locations Sewer Replacement …Chinatown and SOMA Large Diameter Se…Various Locations Sewer Replacement …PW Various Locations Sewer Replacement No 13: construction 21 Feb 2023 to 31 May 2027Beach Street Quick-Build Project: construction 1 Apr 2026 to 31 Dec 2026PW StreetResurfacingPro-BBSR Pavement Prese FY 26-27: construction 1 Jul 2026 to 7 Jul 2027Various Locations Sewer Replacement No 29: construction 12 Jun 2027 to 13 Dec 2028Chinatown and SOMA Large Diameter Sewer Improvements: construction 31 Jul 2027 to 30 Jul 2028Various Locations Sewer Replacement No 35: construction 13 Mar 2028 to 13 Sep 2029Various Locations Pavement Renovation No 86B: construction 30 Oct 2030 to 12 Jan 203221 Feb 2023 – 31 May 20271 Apr 2026 – 31 Dec 20261 Jul 2026 – 7 Jul 202712 Jun 2027 – 13 Dec 202831 Jul 2027 – 30 Jul 202813 Mar 2028 – 13 Sep 202930 Oct 2030 – 12 Jan 2032

Construction start and end as each department publishes them; a dot where only one is published. 1 other project on these street segments publishes no construction dates.

7 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.