Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
PW FOLSOM AREA STORMWATER IMPROVEMENT PROJECT
0% in published scope
Public Works · Sewer, water or power · Design · Under way, ends 31 Dec 2030
1 of the project's 3 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 11th St, 12th St, 15th St, 17th St, 19th St, Alabama St
- Planned bikeway
- Separated bikeway, 0.41 mi on 11th St, Folsom St
- Scope
- None published.
- Dates
Start End Public consultation December 2 December 2 Construction late 2023 2030 - Sources disagree
- The coordination feed gives construction starting 2025-07-01; SFPUC's project page text (“late 2023”), 2023, which is shown.
The coordination feed gives construction ending 2028-09-30; SFPUC's project page text (“2030”), 2030-12-31, which is shown.
The start date has passed (2023) while the phase is still Design, per the coordination feed. - Records
- SFPUC project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Approve an increase of $350,000 to the cost contingency and an increase of 140 calendar days to the duration contingency for Contract No. WW-719A, Folsom Area Stormwater Improvements – SOMA and Mission Districts Sewer Re…28 Jan 2025 · SFPUC Commission · approve Item 12
- Installment Sale Agreement to secure a Clean Water State Revolving Fund Loan for the Wastewater Enterprise Folsom Area Stormwater Improvement Project Phase 224 Sep 2024 · SFPUC Commission · approve agenda item 8 and 9
- Approve an increase of 90 calendar days to the duration contingency for Contract No. WW-719A, Folsom Area Stormwater Improvements28 May 2024 · SFPUC Commission
- Wastewater Enterprise Quarterly Report including Southeast Area Major Projects Update and Biosolids and Headworks26 Mar 2024 · SFPUC Commission
- Ratify correction to Resolution No. 23-0096, approved on May 9, 2023, to increase the construction duration for Contract No. WW-719A, Folsom Area Stormwater Improvements26 Sep 2023 · SFPUC Commission · approve the Consent Calendar
15 earlier
- Resolution approving Modification No. 5 to the Folsom Area Stormwater Improvement Project, Contract No. PRO.0101, Tunnel Engineering Services, with McMillen Jacobs Associates/Stantec, Joint Venture, to increase the contr…25 Jul 2023 · Board of Supervisors · ADOPTED Pass
- Resolution approving Modification No. 5 to the Folsom Area Stormwater Improvement Project, Contract No. PRO.0101, Tunnel Engineering Services, with McMillen Jacobs Associates/Stantec, Joint Venture, to increase the contr…19 Jul 2023 · Board of Supervisors, Budget and Finance Committee · RECOMMENDED Pass
- Resolution approving Modification No. 5 to the Folsom Area Stormwater Improvement Project, Contract No. PRO.0101, Tunnel Engineering Services, with McMillen Jacobs Associates/Stantec, Joint Venture, to increase the contr…27 Jun 2023 · Board of Supervisors
- Modify Contract No. PRO.0101, Tunnel Engineering Services of the Folsom Area Stormwater Improvement Project, with McMillen Jacobs Associates/Stantec, Joint Venture, to increase the Contract amount by $7,500,000 for a new…13 Jun 2023 · SFPUC Commission · approve Item 7
- Award Contract No. WW-719A, Folsom Area Stormwater Improvements – SOMA and Mission Districts Sewer Replacement, to the responsible bidder that submitted the lowest responsive bid, Mitchell Engineering, in the amount of $…9 May 2023 · SFPUC Commission · approve the Consent Calendar
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…9 May 2023 · Board of Supervisors · FINALLY PASSED Pass
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…2 May 2023 · Board of Supervisors · PASSED ON FIRST READING Pass
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…26 Apr 2023 · Board of Supervisors, Budget and Finance Committee · RECOMMENDED Pass
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…12 Apr 2023 · Board of Supervisors
- Approve Amendment No. 4 to Contract No. PRO.0101, Tunnel Engineering Services for the Folsom Area Stormwater Improvements Project, with McMillen Jacobs Associates/ Stantec, Joint Venture11 Apr 2023 · SFPUC Commission · continued
- Ordinance exempting from requirements of the Administrative Code and the Environment Code two agreements between the San Francisco Public Utilities Commission and the California Department of Transportation for professio…11 Apr 2023 · Board of Supervisors
- Recommend that the Board of Supervisors adopt a Special Ordinance that will allow the SFPUC to enter into Cooperative Agreements with Caltrans to perform engineering design review, constructability review and other tech28 Mar 2023 · SFPUC Commission · approve item 9
- Approve Project No. CWWSIPFCDB14, Folsom Area Stormwater Improvements Project, and authorize the General Manager to implement the Project in compliance with the Charter and applicable law, subject to Board of Supervisors…9 Nov 2021 · SFPUC Commission
- Tunnel Engineering Services for the Folsom Area Stormwater Improvement Project with McMillen Jacobs Associates/Stantec10 Aug 2021 · SFPUC Commission · approve Item 9
- Approve Amendment No. 2 to Agreement No. PRO.0101, Tunnel Engineering Services for the Folsom Area Stormwater Improvement Project for an amount not-to-exceed $9,700,00025 Aug 2020 · SFPUC Commission
5 decisions on the same streets, not naming this project
- ESTABLISH – BLUE ZONE 11th Street, west side, from 15 feet to 40 feet south of Folsom Street 11(b). ESTABLISH – GENERAL LOADING ZONE, 5 MIN, AT ALL TIMES, DAILY Folsom Street, south side, from 56 feet to 116 feet west of…2 Aug 2024 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Approving parking and traffic modifications along 17th Street between Potrero Avenue and Mississippi Street to improve transportation safety and connectivity5 Mar 2024 · SFMTA Board · ADOPTED — 7 ayes (Resolution 240305-020)
- Accept work performed by M Squared Construction, Inc., under Contract No. WD-2811, 8- Inch and 16-Inch Ductile Iron Water Main Replacement on 17th Street from Clayton Street to Douglass Street and Various Side Streets; a…9 Jan 2024 · SFPUC Commission · approve items 6a through 6i
- ESTABLISH – CLASS IV BIKEWAY 17th Street, eastbound and westbound, between Potrero Avenue and Mississippi Street (Approvable by the City Traffic Engineer) 4(b). ESTABLISH – STOP SIGNS 17th Street, eastbound and westbound…1 Sep 2023 · Engineering hearing · Item 4(a) corrected to reflect approvability by the City Traffic Engineer. Item 4(c) updated to TOW AWAY NO STOPPING ANY TIME as originally proposed. Items 4(a) through 4(s) approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- ESTABLISH – SPEED TABLES 17th Street, between Market Street and Diamond Street (2 speed tables) 17(b). ESTABLISH – CROSSWALK 17th Street, midblock between Diamond Street and Castro Street 17(c). ESTABLISH – CLASS IV BIKE…18 Oct 2019 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation. Public Comments: Comments received in opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- 7th St, 8th St and Folsom St Pavement RenovationPublic Works · Planning · 6 shared street segments
- Western SOMA and Northern Mission Districts Sewer Replacement WW-719DPublic Works · Design · 3 shared street segments
- FASIP - Western SOMA and Northern Mission District Sewer SystemSFPUC · Design · 3 shared street segments
- 11th Street Safety Improvements ProjectPublic Works · Planning · 3 shared street segments
- Folsom-Howard Streetscape ProjectSFMTA · Current · 2 shared street segments
- Various Locations Pavement Renovation No 87Public Works · Design · 2 shared street segments
- FASIP Harrison/Treat Box Sewer and Connecting Auxiliary Sewers 37” Waterline RelocationSFPUC · Planning · 2 shared street segments
- SFMTA Parking Enforcement HeadquartersPublic Works · Design · 2 shared street segments
How we built this: About the Data