SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Various Locations Pavement Renovation No 102

0% in published scope

Public Works · Repaving · Planning · Starts 30 Apr 2031, ends 12 Jul 2032

Early enough to change: Public Works gives its phase as Planning; its project page may list a contact. No meeting on it is posted for the next 60 days.

1 of the project's 3 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
10th Ave, 16th Ave, 41st Ave, 5th Ave, Balceta Ave, Banbury Dr
Planned bikeway
Shared street, 0.35 mi on Lake St
Would reach
450 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 265 residents with none within about one block (440 feet) today would have one; 515 residents with none within about two blocks (880 feet) today would have one
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
ConstructionApr 2031Jul 2032
Records
Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

7 decisions on the same streets, not naming this project

Construction on these street segments

202520262027202820292030203120322033todayVarious Locations Pavement Renovatio…PW As Needed Spot Sewer Replacement …Various Locations Large Diameter Sew…PW As Needed Spot Sewer Replacement No 47: construction 22 Sep 2025 to 26 Oct 2026Various Locations Large Diameter Sewer Improvements No 1: construction 4 Mar 2027 to 1 Apr 2028Various Locations Pavement Renovation No 102: construction 30 Apr 2031 to 12 Jul 203222 Sep 2025 – 26 Oct 20264 Mar 2027 – 1 Apr 202830 Apr 2031 – 12 Jul 2032

Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.

7 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.