Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Pavement Renovation No 102
0% in published scope
Public Works · Repaving · Planning · Starts 30 Apr 2031, ends 12 Jul 2032
1 of the project's 3 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 10th Ave, 16th Ave, 41st Ave, 5th Ave, Balceta Ave, Banbury Dr
- Planned bikeway
- Shared street, 0.35 mi on Lake St
- Would reach
- 450 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 265 residents with none within about one block (440 feet) today would have one; 515 residents with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Apr 2031 Jul 2032 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
7 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING ANY TIME, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 41st Avenue, east side, from 5 feet to 68 feet north of Quintara Street (63-foot station) (Supervisor District 4) (Approvable by the City T…20 Sep 2024 · Engineering hearing · Continued.
- Approving transit accessibility and active transportation safety improvements on Frida Kahlo Way between Ocean Avenue and Judson Avenue, and on Judson Avenue between Frida Kahlo Way and Foerster Street, including: adding…7 May 2024 · SFMTA Board · ADOPTED — 7 ayes (Resolution 240507-050)
- ESTABLISH – CLASS IV BIKEWAY (TWO-WAY) Frida Kahlo Way, east side, from Cloud Circle (south) to Judson Avenue (establishes two-way protected bikeway, replaces general parking and motorcycle parking) Judson Avenue, south …16 Feb 2024 · Engineering hearing · Corrected some street suffixes and combined 12(s) on agenda into 12(d) on directive. Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 41st Avenue, west side, from 5 feet to 61 feet north of Irving Street (53-foot bike share station with red zones on each side of the station) (Superv…6 Jan 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO RIGHT TURN ON RED 10th Avenue, northbound, at Fulton Street (Supervisor District 1) (Approvable by the City Traffic Engineer) Alison Mathews, [staff email removed — see the order]19 Aug 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 41st Avenue, west side, from 5 feet to 61 feet north of Irving Street (53-foot bike share station with red zones on each side of the station) (Superv…18 Feb 2022 · Engineering hearing · Item withdrawn.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Eucalyptus Drive, south side, from 19 feet to 98 feet west of 20th Avenue (72-foot station with red zones on either side) (Supervisor District 7) Lau…14 Aug 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation. Public Comments: Comments in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.
7 other projects on these street segments
- PW As Needed Spot Sewer Replacement No 47Public Works · Construction · 1 shared street segment
- Outer Sunset Traffic Management ProjectSFMTA · Completed · 1 shared street segment
- Golden Gate Heights Water and Sewer Main Replacement ProjectSFPUC · Construction · 1 shared street segment
- Frida Kahlo Way Quick-Build ProjectSFMTA · Legislated · 1 shared street segment
- Inner Sunset Streetscape Improvement ProjectSFMTA · Completed · 1 shared street segment
- Junipero Serra Boulevard Pavement Renovation & Sewer Replacement ProjectPublic Works · In progress · 1 shared street segment
- Various Locations Large Diameter Sewer Improvements No 1Public Works · Design · 1 shared street segment