Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Laurel Heights/Jordan Park Traffic Calming Project
Not stated
SFMTA · Bike, walk or safety · Implementation / Construction · No start date published, no end date published
8 of the project's 14 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA lists it as a bike project, but does not say whether it builds that bikeway.
- Streets
- Euclid Ave, Arguello Blvd
- Planned bikeway
- Shared street, 1.4 mi on Euclid Ave
Separated bikeway, 0.26 mi on Arguello Blvd - Would reach
- 166 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 8 street segments that lack one. Closer in: 2,002 residents with none within about one block (440 feet) today would have one; 1,001 residents with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Records
- SFMTA project page
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
6 decisions on the same streets, not naming this project
- Award Contract No. WW-743, Geary Boulevard Sewer and Water Improvements Phase 2, to the responsible bidder that submitted the lowest responsive bid, Cratus, Inc., in the amount of $45,957,035, and with a duration of 1,03…25 Jun 2024 · SFPUC Commission
- Accept work performed by M Squared Construction, Inc., Contract No. WD-2692, 16-inch and 8-inch Ductile Iron Water Main Installation and Sewer Replacement on Geary Boulevard from 32nd to 48th Avenues, for a total contrac…23 Nov 2021 · SFPUC Commission · approve Consent Calendar items 10a, 10c, 10d, and 10e
- Accept work performed by JMB Construction, Inc. for Contract No. WW-674R, Geary Boulevard Sewer and Water Improvements; approve Modification No. 2 (final) decreasing the contract amount by $494,459, for a total contract …10 Aug 2021 · SFPUC Commission · approve Consent Calendar items 8a, 8b, and 8d
- Approve increase of $100,000 to the contract cost contingency, and increase of 70 calendar days to the contract duration contingency, for Contract No. WD- 2692, 16-Inch And 8-Inch Ductile Iron Water Main Installation, Se…11 May 2021 · SFPUC Commission · approve Consent Calendar items 8c, 8d, and 8g
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Arguello Boulevard, east side, from 157 feet to 216 feet north of Edward Street (50-foot bike share station with red zones on either end) (Supervisor…1 Nov 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
- ESTABLISH – SIDEWALK BIKE SHARE STATION Arguello Boulevard, east side, from Geary Boulevard to 52 feet northerly (Supervisor District 2) ♦ Laura Stonehill, [staff email removed — see the order] Proposing a Ford GoBike bi…16 Aug 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published.
4 other projects on these street segments
- WD-2936 8-, 12- & 16-inch Ductile Iron Water Main Replacement on Geary Boulevard from Stanyan Street to Presidio Avenue & on Post Street from Presidio Avenue to Scott Street & on Various Side StreetsSFPUC · Design · 7 shared street segments
- PW Various Locations Sewer Replacement No 31Public Works · Design · 2 shared street segments
- Street Resurfacing Program- BBSR Paving FY 26-27Public Works · Construction · 1 shared street segment
- Various Locations Sewer Replacement No 33Public Works · Design · 1 shared street segment
3 documents on the project page