SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

SoMa Slow Streets

Already built

SFMTA · Bike, walk or safety · Legislated · Under way, no end date published

All 2 of the project's street segments on planned bikeway streets already have an all-ages bikeway.

Streets
Folsom St
Planned bikeway
Separated bikeway, 0.17 mi on Folsom St
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
Construction2021not published
Records
SFMTA project page

City decisions naming this project

9 decisions on the same streets, not naming this project

Construction on these street segments

2021202220232024202520262027todaySoMa Slow StreetsFolsom Howard Streetscape Sewer Repl…PW Folsom Streetscape ProjectJoint - Streetscape Lead - Folsom St…Folsom Howard Streetscape Sewer Replacement: construction 11 Mar 2024 to 16 Oct 2026PW Folsom Streetscape Project: construction May 2024 to 16 Oct 2026Joint - Streetscape Lead - Folsom St 10032072: construction May 2024 to 16 Oct 2026SoMa Slow Streets: construction 2021 to end not publishedfrom 202111 Mar 2024 – 16 Oct 2026May 2024 – 16 Oct 2026May 2024 – 16 Oct 2026

Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.

6 other projects on these street segments
1 documents on the project page

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.