Joint - SFWD Lead - PEWS Pipe Contract D - 24-inch

0% in published scope

Public Works · Sewer, water or power · Planning · Starts 3 Jan 2031, ends 31 Dec 2032

Early enough to change: Public Works gives its phase as Planning; its project page may list a contact. No meeting on it is posted for the next 60 days.

All 2 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
40th Ave, 41st Ave, 42nd Ave, Clement St
Planned bikeway
Separated bikeway, 0.23 mi on Clement St
Would reach
No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 146 residents (2020 census) with none within about one block (440 feet) today would have one; 435 residents with none within about two blocks (880 feet) today would have one
Scope
“SFWD lead project with blocks moved from VL85”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJan 2031Dec 2032
Records
Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

5 decisions on the same streets, not naming this project