SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Various Locations Pavement Renovation No 89

0% in published scope

Public Works · Repaving · Design · Starts 28 Jan 2027, ends 12 Apr 2028

Early enough to change: Public Works gives its phase as Design; its project page may list a contact. No meeting on it is posted for the next 60 days.

6 of the project's 9 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
Amazon Ave, Amherst St, Brussels St, Burrows St, Cambridge St, Colby St
Planned bikeway
Shared street, 1.2 mi on Girard St, Silliman St, Somerset St, Cambridge St
Separated bikeway, 0.91 mi on Frida Kahlo Way
Would reach
2,958 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 6 street segments that lack one. Closer in: 2,095 residents, 2 schools with none within about one block (440 feet) today would have one; 1,594 residents, 2 schools with none within about two blocks (880 feet) today would have one
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJan 2027Apr 2028
Records
Public Works contract page (Various Locations Pavement Renovation No. 89 and Sewer Replacement) · Interagency coordination feed record (DataSF row) · When the bid page closes at award, the closest official source: Public Works paving map

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

3 decisions on the same streets, not naming this project

Construction on these street segments

2021202220232024202520262027202820292030todayVarious Locations Pavement Renovatio…Somerset Slow StreetVisitacion Valley and Portola Commun…PW Various Locations Sewer Replaceme…Various Locations Sewer Replacement …PW Various Locations Sewer Replacement (JV VL PR No 89): construction 28 Jan 2027 to 12 Apr 2028Various Locations Sewer Replacement No 34: construction 1 Jun 2028 to 31 May 2029Somerset Slow Street: construction 2021 to end not publishedVisitacion Valley and Portola Community Based Transportation Plan: construction start not published to 31 May 2023Various Locations Pavement Renovation No 89: construction 28 Jan 2027 to 12 Apr 2028from 2021until 31 May 202328 Jan 2027 – 12 Apr 202828 Jan 2027 – 12 Apr 20281 Jun 2028 – 31 May 2029

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.