Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Joint - MTA Lead - Fillmore St Pavement Renovation
0% in published scope
Public Works · Repaving · Planning · Starts 1 Sep 2031, ends 13 Nov 2032
The project's one street segment on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- Bush St, Church St, Eddy St, Ellis St, Fell St, Fillmore St
- Planned bikeway
- Shared street, 0.12 mi on Church St
- Would reach
- No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 181 residents (2020 census) with none within about one block (440 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Sep 2031 Nov 2032 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
6 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Bush Street, north side, from 5 feet to 58 feet east of Leavenworth Street (Supervisor District 3) (Approvable by the City Traffic Engineer)16 May 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WD-2765, 8-Inch and 16-Inch Ductile Iron Water Main Replacement on Jersey Street from Douglass Street to Church Street and Various Street Locations, to the responsible bidder that submitted the lowest …9 Apr 2024 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Fell Street, south side, from 30 feet to 102 feet east of Clayton Street (72-foot station) (Supervisor District 5) (Approvable by the City Traffic En…5 Jan 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approving a permanent Class IV parking protected bikeway and various parking and traffic modifications on Fell Street between Baker Street and Shrader Street as part of the Fell Street Class IV Bikeway Project Approving …20 Jun 2023 · SFMTA Board · ADOPTED — 4 ayes
- Finding that temporarily closing one block of Church Street provides for the safety and protection of transit riders who use the street during the temporary closure due to the large amount of transit riders needing to cr…15 Sep 2020 · SFMTA Board
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Fillmore Street, east side along median, from Jefferson Street to 53 feet southerly (bike share station in angled parking stalls) (Supervisor Distric…17 Jul 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation. Public Comments: Received comments in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Western Addition Community Based Transportation Plan ImplementationSFMTA · Current · 9 shared street segments
- PLN 2526-001: 8-inch Ductile Iron Water Main Replacement on Sutter from Divisadero to Webster, on Pine from Pierce to Gough St, and Various Side StreetsSFPUC · Planning · 8 shared street segments
- Western Addition Area Traffic Signal Upgrades Phase 2SFMTA · Design · 3 shared street segments
- Western Addition Traffic Signal Upgrades Phase 2Public Works · Design · 3 shared street segments
- Various Locations Sewer Replacement No 29Public Works · Design · 2 shared street segments
- WD-2936 8-, 12- & 16-inch Ductile Iron Water Main Replacement on Geary Boulevard from Stanyan Street to Presidio Avenue & on Post Street from Presidio Avenue to Scott Street & on Various Side StreetsSFPUC · Design · 2 shared street segments
- PW Various Locations Sewer Replacement No 16Public Works · Construction · 1 shared street segment
- PW As Needed Spot Sewer Replacement No 47Public Works · Construction · 1 shared street segment
How we built this: About the Data