Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
16th St, 17th St, and 18th St Pavement Renovation
0% in published scope
Public Works · Repaving · Planning · Starts 30 Aug 2033, ends 13 Nov 2034
2 of the project's 10 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 16th St, 17th St, 18th St, Connecticut St, Kansas St, Vermont St
- Planned bikeway
- Separated bikeway, 0.85 mi on 17th St
Level 3 shared street, 0.18 mi on Connecticut St
Shared street, 0.18 mi on Kansas St - Would reach
- 1,230 residents (2020 census), 2 schools, 1 library would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 1,001 residents with none within about one block (440 feet) today would have one; 922 residents, 1 school with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Aug 2033 Nov 2034 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
7 decisions on the same streets, not naming this project
- Approve an increase in the amount of $2,500,000 to the cost contingency and an increase of 100 calendar days to the duration contingency for Contract No. WW-736, Castro and Mission Districts Sewer Improvements, with Prec…14 May 2024 · SFPUC Commission
- Approving parking and traffic modifications along 17th Street between Potrero Avenue and Mississippi Street to improve transportation safety and connectivity5 Mar 2024 · SFMTA Board · ADOPTED — 7 ayes (Resolution 240305-020)
- Accept work performed by M Squared Construction, Inc., under Contract No. WD-2811, 8- Inch and 16-Inch Ductile Iron Water Main Replacement on 17th Street from Clayton Street to Douglass Street and Various Side Streets; a…9 Jan 2024 · SFPUC Commission · approve items 6a through 6i
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES 18th Street, north side, from 82 feet to 101 feet west of Guerrero Street (Supervisor District 8) (Approvable by the City Traffic Engineer) Jason Hyde, [staff email remove…8 Dec 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – CLASS IV BIKEWAY 17th Street, eastbound and westbound, between Potrero Avenue and Mississippi Street (Approvable by the City Traffic Engineer) 4(b). ESTABLISH – STOP SIGNS 17th Street, eastbound and westbound…1 Sep 2023 · Engineering hearing · Item 4(a) corrected to reflect approvability by the City Traffic Engineer. Item 4(c) updated to TOW AWAY NO STOPPING ANY TIME as originally proposed. Items 4(a) through 4(s) approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Hearing of persons interested in or objecting to the determination of exemption from environmental review under the California Environmental Quality Act issued as a Statutory Exemption by the Planning Department on June …13 Sep 2021 · Board of Supervisors · Filed without a hearing
- ESTABLISH – SPEED TABLES 17th Street, between Market Street and Diamond Street (2 speed tables) 17(b). ESTABLISH – CROSSWALK 17th Street, midblock between Diamond Street and Castro Street 17(c). ESTABLISH – CLASS IV BIKE…18 Oct 2019 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation. Public Comments: Comments received in opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 12 shared street segments
- WD-2919: 8- and 12-Inch Ductile Iron Water Main Replacement on 18th and Mariposa Streets from Potrero Ave. to Texas St. and on Various Side StreetsSFPUC · Design · 2 shared street segments
- 17th Street Quick-BuildSFMTA · Project Evaluation · 2 shared street segments
- PW As Needed Spot Sewer Replacement No 47Public Works · Construction · 1 shared street segment
- WD-2877 As Needed Water Main Replacement No.3SFPUC · Design · 1 shared street segment
- Various Locations Sewer Replacement No 29Public Works · Design · 1 shared street segment
- Bryant Street Bike Network Improvement ProjectSFMTA · Completed · 1 shared street segment
- PW Various Locations Sewer Replacement No 16Public Works · Construction · 1 shared street segment
How we built this: About the Data