Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
PW Various Locations Sewer Replacement No 17
0% in published scope
Public Works · Sewer, water or power · Design · Under way, ends 15 Nov 2026
6 of the project's 8 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 15th Ave, 18th St, 20th St, 21st St, 22nd Ave, 23rd Ave
- Planned bikeway
- Shared street, 1.1 mi on Greenwich St, Francisco St, 15th Ave, Baker St
- Would reach
- No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 6 street segments that lack one. Closer in: 1,125 residents (2020 census) with none within about one block (440 feet) today would have one
- Scope
- “WW-729, 2219i”
- Dates
Start End Public consultation not published not published Construction Nov 2024 Nov 2026 - Sources disagree
- The start date has passed (2024-11-14) while the phase is still Design, per the coordination feed.
- Records
- SFPUC contract page (WW-729 Various Locations Sewer Replacement No. 17) · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Award Contract No. WW-729, Various Locations Sewer Replacement No. 17, to the responsible bidder that submitted the lowest responsive bid, J. Flores Construction Company, Inc12 Nov 2024 · SFPUC Commission
10 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKESHARE STATION Jones Street, west side, from Sacramento Street to 35 feet northerly (Supervisor District 3) (Approvable by the City Traffic Engineer)12 Jun 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING ANY TIME, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 23rd Avenue, east side, from 10 feet to 73 feet south of Sloat Boulevard (63-foot station) (Supervisor District 4) (Approvable by the City …20 Sep 2024 · Engineering hearing · Continued.
- Approve an increase in the amount of $2,500,000 to the cost contingency and an increase of 100 calendar days to the duration contingency for Contract No. WW-736, Castro and Mission Districts Sewer Improvements, with Prec…14 May 2024 · SFPUC Commission
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 15th Avenue, north side, from 5 feet to 67 feet west of Portola Drive (62-foot bike share station) (Supervisor District 7) (Approvable by the City T…22 Mar 2024 · Engineering hearing · Item withdrawn.
- Accept work performed by Trinet Construction, Inc. for Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair; approve Modification No. 1 (Final) decreasing the Contract amoun…23 Jan 2024 · SFPUC Commission · approve items 7a through 7i
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES 18th Street, north side, from 82 feet to 101 feet west of Guerrero Street (Supervisor District 8) (Approvable by the City Traffic Engineer) Jason Hyde, [staff email remove…8 Dec 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair, in the amount of $566,000, and with a duration of 240 consecutive calendar days, to the responsible bidder that s…10 Jan 2023 · SFPUC Commission · Approve Consent Calendar Items 6a through 6j
- Approve an increase of $2,250,000 to the contract cost contingency, and an increase of 180 consecutive calendar days to the contract duration contingency for Contract No. WW-712, New Montgomery, Jessie, Minna, and Missio…8 Feb 2022 · SFPUC Commission · approve Item 10
- Hearing of persons interested in or objecting to the determination of exemption from environmental review under the California Environmental Quality Act issued as a Statutory Exemption by the Planning Department on June …13 Sep 2021 · Board of Supervisors · Filed without a hearing
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Greenwich Street, north side, from Franklin Street to 90 70 feet easterly (7270-foot bike share station with red zones on either side) (Supervisor Di…18 Oct 2019 · Engineering hearing · Approved by the City Traffic Engineer for implementation with modifications as noted above. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Main Street Streetscape ProjectSFMTA · Detailed Design · 7 shared street segments
- PW Main St Streetscape Drainage ImprovementsPublic Works · Construction · 4 shared street segments
- Slow StreetsSFMTA · Construction · 3 shared street segments
- PW Various Locations Sewer Replacement No 18Public Works · Construction · 3 shared street segments
- Street Resurfacing Program- BBSR Paving FY 26-27Public Works · Construction · 2 shared street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 2 shared street segments
- PW Contract 35 Traffic Signal UpgradePublic Works · Construction · 1 shared street segment
- Transbay Howard Streetscape Improvement ProjectSFMTA · Implementation / Construction · 1 shared street segment
How we built this: About the Data