Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Golden Gate Park Access and Safety Program
Builds 45%
SFMTA · Bike, walk or safety · Legislated · Under way, ends 31 Dec 2028
4 of the project's 25 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 2.7 mi of the plan's bikeway.
- Streets
- John F Kennedy Dr, Middle West Dr, Martin Luther King Jr Dr, Overlook Dr, Transverse Dr, Conservatory Dr West
- Planned bikeway
- Car-free street, 6.9 mi on John F Kennedy Dr, Martin Luther King Jr Dr, Middle West Dr, Overlook Dr
Separated bikeway, 1.6 mi on Middle West Dr, Transverse Dr, Martin Luther King Jr Dr, John F Kennedy Dr
Shared street, 0.52 mi on Conservatory Dr West, 8th Ave
Bikeway of undecided type, 0.14 mi on Chain Of Lakes Dr - Scope
- “The Golden Gate Park Access Project aims to improve existing gaps in the biking and rolling network to better connect the car-free JFK Promenade with the multi-use Panhandle Path, the existing Fell Street bikeway, the proposed Oak Street Quick-Build bikeway, and the shared-use path leading to Page Slow Street. Potential improvements include two-way bikeway between Golden Gate Park entrance and Shrader Street, new signals at JFK/Kezar, intersection realignment at JFK/Kezar, shared-use path realignment from Page to Kezar, and landscaping.”
- Dates
Start End Public consultation Summer-Fall 2021 Summer-Fall 2021 Construction Feb 2025 Dec 2028 - Sources disagree
- SFMTA's project page gives construction starting 2022-04, a stage it still marks Pending; the coordination feed gives 2025-02-01, which is shown.
SFMTA gives the phase as Legislated; the coordination feed gives Planning. - Records
- SFMTA project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Hearing to consider the proposed Initiative Ordinance submitted by four or more Supervisors to the voters for the November 8, 2022, Election, entitled "Ordinance amending the Park Code to repeal and reauthorize the Golde…18 Jul 2022 · Board of Supervisors, Rules Committee · HEARD AND FILED Pass
- Hearing on updates and to report on the economic recovery of San Francisco's arts and cultural institutions, including an update and report on the status of the implementation of the Golden Gate Park Access and Safety Pr…14 Jul 2022 · Board of Supervisors, Public Safety and Neighborhood Services Committee · CONTINUED TO CALL OF THE CHAIR Pass
- Hearing to consider the proposed Initiative Ordinance submitted by four or more Supervisors to the voters for the November 8, 2022, Election, entitled "Ordinance amending the Park Code to repeal and reauthorize the Golde…28 Jun 2022 · Board of Supervisors
- Ordinance amending the Park Code to adopt the Golden Gate Park Access and Safety Program, which includes restricting private vehicles on certain slow street segments in Golden Gate Park including on John F. Kennedy Drive…3 May 2022 · Board of Supervisors · Passed
- Park Code - Golden Gate Park Access and Safety Program - Slow Street Road Closures - Modified Configuration26 Apr 2022 · SFCTA Board
7 earlier
- Hearing on updates and to report on the economic recovery of San Francisco's arts and cultural institutions, including an update and report on the status of the implementation of the Golden Gate Park Access and Safety Pr…26 Apr 2022 · Board of Supervisors
- Ordinance amending the Park Code to adopt the Golden Gate Park Access and Safety Program, which includes restricting private vehicles on certain slow street segments in Golden Gate Park including on John F. Kennedy Drive…26 Apr 2022 · Board of Supervisors · Re-referred as amended
- Motion calling from the Land Use and Transportation Committee, pursuant to Board Rule 3.37, the proposed Ordinance amending the Park Code to adopt the Golden Gate Park Access and Safety Plan (File No. 220261) and another…12 Apr 2022 · Board of Supervisors · APPROVED Pass
- Motion calling from the Land Use and Transportation Committee, pursuant to Board Rule 3.37, the proposed Ordinance amending the Park Code to adopt the Golden Gate Park Access and Safety Plan (File No. 220261) and another…5 Apr 2022 · Board of Supervisors
- Ordinance amending the Park Code to adopt the Golden Gate Park Access and Safety Program, which includes restricting private vehicles on certain slow street segments in Golden Gate Park including on John F. Kennedy Drive…5 Apr 2022 · Board of Supervisors
- Ordinance amending the Park Code to adopt the Golden Gate Park Access and Safety Program, which includes restricting private vehicles on certain slow street segments in Golden Gate Park including on John F. Kennedy Drive…15 Mar 2022 · Board of Supervisors
- GOLDEN GATE PARK ACCESS AND SAFETY PROGRAM10 Mar 2022 · SFMTA Board · ADOPTED — 7 ayes (Resolution 220310-020)
6 milestones and events from the project's own page
- Implementation & EvaluationSpring 2022 · Project page timeline · Pending
- Board of Directors special meeting, March 10, 202210 Mar 2022 · Project page event
- Proposal at Board of SupervisorsWinter 2021/22 · Project page timeline · Completed
- Golden Gate Park Access & Safety Program: Bike & Talk Tour20 Nov 2021 · Project page event
- Golden Gate Park Access & Safety Program: Walk/Roll & Talk Tour10 Oct 2021 · Project page event
- Public Outreach & Technical AnalysisSummer-Fall 2021 · Project page timeline · Completed
5 decisions on the same streets, not naming this project
- Award a five-year lease, to C5 Children’s School for the childcare center premises at 525 Golden Gate Avenue in San Francisco for an annual $1 rent10 Dec 2024 · SFPUC Commission · approve Item 8
- Approving protected bikeway and traffic modifications on Lincoln Way and Sloat Boulevard, endorsing the closure of the Upper Great Highway and adopting the closure and findings of Proposition K3 Dec 2024 · SFMTA Board · ADOPTED — 5 ayes, 1 nay (Resolution 241203-134)
- ESTABLISH – NO RIGHT TURN ON RED 10th Avenue, northbound, at Fulton Street (Supervisor District 1) (Approvable by the City Traffic Engineer) Alison Mathews, [staff email removed — see the order]19 Aug 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – ESTABLISH - RIGHT LANES MUST TURN RIGHT ESTABLISH – NO LEFT TURNS, NO U-TURNS ESTABLISH – NO RIGHT TURN ON RED Lincoln Way, westbound at Upper Great Highway (Approvable by the City Traffic Engineer) 16(b). ES…4 Jun 2021 · Engineering hearing · Continued.
- Accept work performed by Marinship Development Interest, LLC, for Contract No. WW-694, Lincoln Way/48th Ave Diversion Structure Modification; approve Modification No. 1 (Final), decreasing the contract amount by $7,400, …9 Feb 2021 · SFPUC Commission · approve Consent Calendar items 9a through 9d
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Golden Gate Park Traffic Safety ProjectSFMTA · Completed · 37 shared street segments
- Oak Street Quick-Build ProjectSFMTA · 7 shared street segments
- WD-2922: 8-inch Ductile Iron Water Main Replacement on Lincoln Way from Sunset to La Playa St and Various Side StreetsSFPUC · Design · 3 shared street segments
- PEFWS Pipeline Contract E - 24-inch GGP CrossingSFPUC · Planning · 3 shared street segments
- Outer Sunset Traffic Management ProjectSFMTA · Completed · 1 shared street segment
- Great Highway Pilot ProjectSFMTA · Completed · 1 shared street segment
- Lincoln and Sloat Quick-Build Connections ProjectSFMTA · 1 shared street segment
- 14-009 8-, and 24-inch Ductile Iron Water Main Replacement on Page Street from Stanyan to Fillmore StreetsSFPUC · Design · 1 shared street segment
How we built this: About the Data