Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
8th St, Clay St and Leavenworth St Pavement Renovation and Sewer Replacement
Already built
Public Works · Repaving · Construction · Under way, ends 27 Oct 2026
All 7 of the project's street segments on planned bikeway streets already have an all-ages bikeway.
- Streets
- 7th St, 8th St, Clay St, Gordon St, Harrison St, Larkin St
- Planned bikeway
- Separated bikeway, 0.32 mi on 8th St, 7th St
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Feb 2025 Oct 2026 - Sources disagree
- The coordination feed gives construction ending 2026-10-27, which is shown; Public Works' project page (Completion “Spring, 2026”; text “Spring, 2026”) gives 2026-05-31, an end that has passed while the page still gives the job as In progress.
- Records
- Public Works project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- 8th St., Clay St., and Leavenworth St. Pavement Renovation and Sewer Replacement: Extend contract duration by 185 calendar days1 May 2026 · Delegated contract change (Public Works) · Contract change approved by the Director
- 8th Street, Clay Street, and Leavenworth Street Pavement Renovation and Sewer Replacement - Contract Modification9 Apr 2026 · Public Works Commission
- 8th Street, Clay Street, and Leavenworth Street Pavement Renovation and Sewer Replacement - Contract Award28 Oct 2024 · Public Works Commission
9 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKESHARE STATION Clay Street, north side, from Davis Street to 66 feet westerly (Supervisor District 3) (Approvable by the City Traffic Engineer)12 Jun 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – SIDEWALK BIKE SHARE STATION Clay Street, south side, from 20 feet to 120 feet east of Battery Street (Supervisor District 3) (Approvable by the City Traffic Engineer) Laura Stonehill, [staff email removed — s…19 Jul 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Accept work performed by Pipe and Plant Solutions, Inc., under Contract No. WW-675, 5th/18th/Upper Larkin Street Sewer Inspection; approve Modification No. 2 (Final) decreasing contract amount by $10,000, for a total con…12 Mar 2024 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Larkin Street, east side, from California Street to 70 feet southerly (62-foot station with red zones) (Supervisor District 3) (Approvable by the Ci…6 Oct 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of $180,000 to the contract cost contingency, and an increase of 180 calendar days to the contract duration contingency, for Contract No. WW-675, 5th/18th/Upper Larkin Street Sewer Inspection; and aut…28 Feb 2023 · SFPUC Commission · approve Consent Calendar Items 6a through 6d
- ESTABLISH – NO RIGHT TURN ON RED Harrison Street, westbound, at 7th Street (Supervisor District 6) (Approvable by the City Traffic Engineer) Alison Mathews, [staff email removed — see the order]20 Jan 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Harrison Street, west side, from 9 feet to 66 feet north of 14th Street (Supervisor District 9) (Approvable by the City Traffic Engineer) Laura Stone…21 Oct 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Clay Street, south side, from 138 feet to 206 feet east of Lyon Street (63-foot bike share station in parking lane with red zones on either side) (Su…3 Jun 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 8th Street, east side, from 18 feet to 57 feet south of Hooper Street (35-foot bike share station with red zones on either side) (Supervisor District…5 Nov 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.
7 other projects on these street segments
- 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation)Public Works · Construction · 13 shared street segments
- 7th Street and 8th Street Safety ProjectsSFMTA · Completed · 9 shared street segments
- Bikeway HardeningSFMTA · Planning · 4 shared street segments
- Mission, 8th, 9th, Howard and Natoma Brick Sewer RehabilitationPublic Works · Construction · 4 shared street segments
- Folsom-Howard Streetscape ProjectSFMTA · Current · 3 shared street segments
- Better Market StreetSFMTA · Current · 1 shared street segment
- As Needed Paving Contract No.15 - Natoma StPublic Works · Design · 1 shared street segment
How we built this: About the Data