Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
PW Various Locations Sewer Replacement No 19
0% in published scope
Public Works · Sewer, water or power · Design · Starts 3 Mar 2027, ends 1 May 2028
1 of the project's 4 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 2nd Ave, 4th Ave, Anza St, Baker St, Beideman St, Broderick St
- Planned bikeway
- Shared street, 0.35 mi on Clay St, Cabrillo St, Anza St
Separated bikeway, 0.13 mi on Masonic Ave - Would reach
- No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 212 residents (2020 census) with none within about one block (440 feet) today would have one
- Scope
- “2467i”
- Dates
Start End Public consultation not published not published Construction Mar 2027 May 2028 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Sewer Upgrades: Renewal & Replacement Program
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
14 decisions on the same streets, not naming this project
- RESCIND – CLASS III BIKE LANE Baker Street, southbound, from Fell Street to Oak Street 38(b). RESCIND – ANGLED PARKING ESTABLISH – PARALLEL PARKING Baker Street, west side, between Oak Street and Fell Street 38(c). ESTAB…8 Nov 2024 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- RESCIND – CLASS III BIKE LANE Baker Street, southbound, from Fell Street to Oak Street 8(b). RESCIND – ANGLED PARKING ESTABLISH – PARALLEL PARKING Baker Street, west side, between Oak Street and Fell Street 8(c). ESTABLI…18 Oct 2024 · Engineering hearing · Item withdrawn by staff.
- Award Contract No. WD-2844, 12-Inch Ductile Iron Water Main Installation on Parnassus Avenue, from Stanyan Street to 6th Avenue, on Lawton Street from 7th Avenue to Funston Avenue, and Various Street Locations, to the re…24 Sep 2024 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. WW-743, Geary Boulevard Sewer and Water Improvements Phase 2, to the responsible bidder that submitted the lowest responsive bid, Cratus, Inc., in the amount of $45,957,035, and with a duration of 1,03…25 Jun 2024 · SFPUC Commission
- Approve an increase of 185 calendar days to the contract duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a new contract duration limit of up to 570…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- Accept work performed by Trinet Construction, Inc. for Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair; approve Modification No. 1 (Final) decreasing the Contract amoun…23 Jan 2024 · SFPUC Commission · approve items 7a through 7i
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Anza Street, north side, from 6 feet to 61 feet east of 19th Avenue (Supervisor District 1) (Approvable by the City Traffic Engineer) Daniel Mackowsk…18 Aug 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair, in the amount of $566,000, and with a duration of 240 consecutive calendar days, to the responsible bidder that s…10 Jan 2023 · SFPUC Commission · Approve Consent Calendar Items 6a through 6j
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Pierce Street, east side, from Chestnut Street to 48 feet southerly (43-foot bike share station in parking lane with red zones on either side) (Super…18 Mar 2022 · Engineering hearing · Item withdrawn.
- All matters listed hereunder constitute a Consent Calendar, are considered to be routine by the San Francisco Municipal Transportation Agency Board of Directors and will be acted upon by a single vote. There will be no s…15 Jun 2021 · SFMTA Board · ADOPTED — 6 ayes
- Accept work performed by Cratus, Inc. for Contract No. WD-2614, 8-Inch Ductile Iron Water Main Replacement on Green Street from Gough Street to Broderick Street; approve Modification No. 2 (Final), decreasing the contrac…8 Jun 2021 · SFPUC Commission · approve the Consent Calendar 8a through 8e
- ESTABLISH – CLASS II BIKEWAY A. Anza Street, eastbound, south side, between 30th Avenue and Parker Avenue (Requires approval of the SFMTA Board) B. Anza Street, eastbound, south side, between Blake Street and Masonic Ave…30 Apr 2021 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation after completion of environmental approval.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Anza Street, south side, from 157 feet to 206 feet west of crosswalk at Collins Street (bike share station with back-to-back plates) (Supervisor Dist…24 Jan 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: No comments received.
- ESTABLISH – NO PARKING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Divisadero Street, east side, from 20.5 feet to 76.5 feet south of Clay Street (52’-8” bike share station with a 3’ red zone south of the station) (Su…18 Oct 2019 · Engineering hearing · Hold. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 6 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Slow StreetsSFMTA · Construction · 3 shared street segments
- Telegraph Hill Rock Slope ImprovementsPublic Works · In progress · 2 shared street segments
- Hayes St, Fell St and Van Ness Ave Pavement RenovationPublic Works · Planning · 1 shared street segment
- 2274I_PW_Automated_Photo_Enforcement_System_Upgrade_Contract_2Public Works · Construction · 1 shared street segment
- Golden Gate Park Traffic Safety ProjectSFMTA · Completed · 1 shared street segment
- PW StreetResurfacingPro-BBSR Pavement Prese FY 26-27Public Works · Construction · 1 shared street segment
- Anza Street Bike Lanes ProjectSFMTA · Planning · 1 shared street segment
- Masonic Avenue Streetscape ProjectSFMTA · Completed · 1 shared street segment
How we built this: About the Data