Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

18th St and Valencia St Pavement Renovation

0% in published scope

Public Works · Repaving · Planning · Starts 28 Dec 2032, ends 13 Mar 2034

Early enough to change: Public Works gives its phase as Planning; its project page may list a contact. No meeting on it is posted for the next 60 days.

4 of the project's 19 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
18th St, Valencia St
Planned bikeway
Separated bikeway, 2.8 mi on Valencia St
Would reach
0 residents (2020 census), 2 schools would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 4 street segments that lack one. Closer in: 1,446 residents, 1 school with none within about one block (440 feet) today would have one; 253 residents, 3 schools with none within about two blocks (880 feet) today would have one
Scope
None published.
Dates
StartEnd
Public consultationnot publishednot published
ConstructionDec 2032Mar 2034
Records
Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

14 decisions on the same streets, not naming this project

Construction on these street segments

20252026202720282029203020312032203320342035today18th St and Valencia St Pavement Ren…PW Various Locations Sewer Replaceme…PW As Needed Spot Sewer Replacement …Mission District Sewer Rehabilitatio…PW Various Locations Sewer Replacement No 16: construction 8 Sep 2025 to 9 Feb 2027PW As Needed Spot Sewer Replacement No 47: construction 22 Sep 2025 to 26 Oct 2026Mission District Sewer Rehabilitation (VLLD2B): construction 7 Jun 2027 to 6 Jun 202818th St and Valencia St Pavement Renovation: construction 28 Dec 2032 to 13 Mar 20348 Sep 2025 – 9 Feb 202722 Sep 2025 – 26 Oct 20267 Jun 2027 – 6 Jun 202828 Dec 2032 – 13 Mar 2034

Construction start and end as each department publishes them; a dot where only one is published. 1 other project on these street segments publishes no construction dates.

4 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.