SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Bikeway Hardening

Not stated

SFMTA · Bike, walk or safety · Planning · Under way, ends 30 Jun 2027

8 of the project's 77 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope names bike work, but does not say whether it builds that bikeway.

Streets
13th St, 16th St, 2nd St, 4th St, 7th St, 8th St
Planned bikeway
Separated bikeway, 13 mi on John Muir Dr, 7th St, Polk St, Brotherhood Way
Shared street, 0.34 mi on Market St
Would reach
1,239 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 8 street segments that lack one. Closer in: 309 residents with none within about one block (440 feet) today would have one; 0 residents, 1 school with none within about two blocks (880 feet) today would have one
Scope
“Over the past decade, the SFMTA has installed Class IV bikeways with flex posts & paint buffers as part of the quick-build program. While many of these projects have improved overall safety for people who bike, scoot, and roll, it is prudent for staff to revisit these locations to observe how they are working and identify locations that would be good candidates for doweled in concrete islands. This programmatic effort is in support of the City goal of creating a citywide bike network that is safe and comfortable for all ages and abilities. This work will also provide an established process for staff to upgrade bikeways in a systems manner into the future.”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionJul 2025Jun 2027
Sources disagree
The start date has passed (2025-07-01) while the phase is still Planning, per the coordination feed.
Records
Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

24 decisions on the same streets, not naming this project

Construction on these street segments

20222024202620282030203220342036todayBikeway HardeningBayview Community Based Transportati…13th Street Safety ProjectPW Various Locations Sewer Replaceme…7th St, 8th St and Folsom St Pavemen…Brotherhood Way Pavement Renovation13th Street Safety Project: construction 3 Feb 2025 to 31 Dec 2026PW Various Locations Sewer Replacement (JV VL PR No 62): construction Apr 2025 to 30 Sep 20267th St, 8th St and Folsom St Pavement Renovation: construction 28 Jun 2030 to 10 Sep 2031Brotherhood Way Pavement Renovation: construction 19 Jul 2034 to 1 Oct 2035Bayview Community Based Transportation Plan: construction 2022 to end not publishedBikeway Hardening: construction 1 Jul 2025 to 30 Jun 20271 Jul 2025 – 30 Jun 2027from 20223 Feb 2025 – 31 Dec 2026Apr 2025 – 30 Sep 202628 Jun 2030 – 10 Sep 203119 Jul 2034 – 1 Oct 2035

Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.

8 other projects on these street segments