Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Bikeway Hardening
Not stated
SFMTA · Bike, walk or safety · Planning · Under way, ends 30 Jun 2027
8 of the project's 77 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope names bike work, but does not say whether it builds that bikeway.
- Streets
- 13th St, 16th St, 2nd St, 4th St, 7th St, 8th St
- Planned bikeway
- Separated bikeway, 13 mi on John Muir Dr, 7th St, Polk St, Brotherhood Way
Shared street, 0.34 mi on Market St - Would reach
- 1,239 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 8 street segments that lack one. Closer in: 309 residents with none within about one block (440 feet) today would have one; 0 residents, 1 school with none within about two blocks (880 feet) today would have one
- Scope
- “Over the past decade, the SFMTA has installed Class IV bikeways with flex posts & paint buffers as part of the quick-build program. While many of these projects have improved overall safety for people who bike, scoot, and roll, it is prudent for staff to revisit these locations to observe how they are working and identify locations that would be good candidates for doweled in concrete islands. This programmatic effort is in support of the City goal of creating a citywide bike network that is safe and comfortable for all ages and abilities. This work will also provide an established process for staff to upgrade bikeways in a systems manner into the future.”
- Dates
Start End Public consultation not published not published Construction Jul 2025 Jun 2027 - Sources disagree
- The start date has passed (2025-07-01) while the phase is still Planning, per the coordination feed.
- Records
- Interagency coordination feed record (DataSF row)
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
24 decisions on the same streets, not naming this project
- Award Contract No. WW-795, Sansome Street Outfall Improvements, to the responsible bidder that submitted the lowest responsive bid, R&S Construction Management, Inc., in the amount of $3,322,700 and with a duration of 30…9 Dec 2025 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. WW-790, Evans Ave. and Mariposa St. Outfalls Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $2,576,348, with a duration of 379 con…9 Sep 2025 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. WW-757R, Laguna, Howard, and Mission Creek Combined Sewer Discharge Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $7,296,786, wit…13 May 2025 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES 4th Street, east side, from 10 feet to 30 feet south of Mission Rock Street (Supervisor District 6) (Approvable by the City Traffic Engineer) Grant Brokl, [staff email rem…18 Apr 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- RESCIND – NO PARKING ANY TIME, EXCEPT BICYCLES 4th Street, east side, from 17 feet to 40 feet north of Minna Street 8(b). ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Minna Street, south side, from 122 feet to 143 fe…7 Mar 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of 155 calendar days to the duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for SFPUC DECEMBER 10, 2024 MEETING MINUTES Page 6 of 1…10 Dec 2024 · SFPUC Commission · approve Item 13
- Approve an increase of 90 calendar days to the duration contingency and increase of $200,000 to the amount contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a…25 Jun 2024 · SFPUC Commission
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 4th Street, west side, from 19 feet to 50 feet north of King Street (31-foot bike share station) (Supervisor District 6) (Approvable by the City Tra…14 Jun 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of 185 calendar days to the contract duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a new contract duration limit of up to 570…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- Approve an increase of $215,000 to the contract cost contingency and an increase of 50 calendar days to the contract duration contingency for Contract No. WW-707R, Various Locations Sewer Replacement No. 11, with Basset …26 Sep 2023 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Polk Street, west side, from 31 feet to 96 feet south of Bush Street (62-foot station with red zones on either side) (Supervisor District 3) (Approv…22 Sep 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH - NO PARKING ANY TIME, EXCEPT BICYCLES 4th Street, east side, from 17 feet to 40 feet north of Minna Street (Supervisor District 6) (Approvable by the City Traffic Engineer) Jason Hyde, [staff email removed — s…19 May 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – CLASS IV BIKEWAY (PARKING PROTECTED BIKEWAY) Bayshore Boulevard, northbound and southbound, between Silver Avenue and Oakdale Avenue 13(b). ESTABLISH – TRANSIT BOARDING ISLAND Bayshore Boulevard, east side, f…17 Mar 2023 · Engineering hearing
- Approve an increase of $2,250,000 to the contract cost contingency, and an increase of 180 consecutive calendar days to the contract duration contingency for Contract No. WW-712, New Montgomery, Jessie, Minna, and Missio…8 Feb 2022 · SFPUC Commission · approve Item 10
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 4th Street, west side, from Gene Friend Way to 103 feet northerly (92-foot bike share station with red zones on each side of the station) (Supervisor…5 Nov 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- ESTABLISH – CLASS IV PROTECTED BIKEWAY Polk Street, southbound, from Grove Street to Hayes Street (Approvable by the City Traffic Engineer) 18(b). ESTABLISH – TOW AWAY NO STOPPING ANYTIME Polk Street, west side, from Gro…3 Sep 2021 · Engineering hearing · Items (a), (c), (d) and (e) approved by the City Traffic Engineer for implementation. Item (b) approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- ESTABLISH - NO PARKING ANYTIME EXCEPT BICYCLES 4th Street, east side, from 103 feet to 144 feet south of Campus Way (Approvable by the City Traffic Engineer) 14(b). ESTABLISH - PASSENGER LOADING ZONE AT ALL TIMES 4th Str…4 Jun 2021 · Engineering hearing · Approved by the City Traffic Engineer to add subsection 14(c) for clarity and tor implementation. #
- Approving temporarily prohibiting the use of northbound 4th Street between Berry and Channel Streets by all vehicles other than transit, buses, bicycles, taxis, and emergency vehicles; directing the City Traffic Engineer…5 Jan 2021 · SFMTA Board · ADOPTED — 5 ayes
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 7th Street, east side, from 4 feet to 54 feet north of Brannan Street (50-foot bike share station) (Supervisor District 6) Pallavi Panyam, [staff ema…16 Oct 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation. The Environmental Review citation, Case 2015-005492ENV, is accurate since temporary station installation and/or relocation are included in the bike share system.
- RESCIND - NO PARKING ANY TIME EXCEPT BICYCLES Hayes Street, north side, from 29 feet west to 49 feet west of Octavia Street 6(b). ESTABLISH - GENERAL METERED PARKING, 4-HOUR TIME LIMIT, 9AM TO 6PM, MONDAY THROUGH SATURDA…18 Sep 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- 20(a). ESTABLISH – CLASS IV PROTECTED BIKEWAY Berry Street, westbound, north side, between 3rd Street and 4th Street 20(b). ESTABLISH – TOW-AWAY, NO STOPPING ANYTIME Berry Street, north side, from 4th Street to 449 feet …21 Feb 2020 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation after environmental clearance has been obtained. Public Comments: Comments received in support and opposition. # comment applies to items 20(c) – 20(f).
- 12(a). ESTABLISH – CLASS IV BIKEWAY (PARKING PROTECTED BIKEWAY) Division Street, eastbound, south side, between San Bruno Avenue and Vermont Street (curbside bike lane with buffer and floating parking) Division Street, w…21 Feb 2020 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation. Public Comments: No comments received. # footnote applies to item 12(c).
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 7th Street, east side, from 17 to 106 feet north of King Street (70-foot bike share station in hatched area) (Supervisor District 6) Laura Stonehill,…18 Oct 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Townsend Street, north side, from 27 feet 124 feet west of 5th Street (expanding existing bike share station to the west by 15 feet) ♦ 11(b). ESTABLI…13 Sep 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: One comment in opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- 7th Street and 8th Street Safety ProjectsSFMTA · Completed · 16 shared street segments
- Brotherhood Way Pavement RenovationPublic Works · Planning · 9 shared street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 7 shared street segments
- Bayview Community Based Transportation PlanSFMTA · Planning · 7 shared street segments
- PW Various Locations Sewer Replacement (JV VL PR No 62)Public Works · Construction · 6 shared street segments
- 13th Street Safety ProjectSFMTA · Implementation / Construction · 6 shared street segments
- 7th St, 8th St and Folsom St Pavement RenovationPublic Works · Planning · 6 shared street segments
- Division/13th Street Safety ProjectSFMTA · Completed · 5 shared street segments
How we built this: About the Data