Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
PW Various Locations Sewer Replacement (JV VL PR No 90)
0% in published scope
Public Works · Sewer, water or power · Construction · Under way, ends 12 Oct 2027
2 of the project's 3 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 14th Ave, 15th Ave, 7th Ave, Clarendon Ave, Corbett Ave, Encline Ct
- Planned bikeway
- Separated bikeway, 0.69 mi on Laguna Honda Blvd
Shared street, 0.12 mi on Corbett Ave - Would reach
- 2,952 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 1,198 residents with none within about one block (440 feet) today would have one; 1,654 residents with none within about two blocks (880 feet) today would have one
- Scope
- “2501i”
- Dates
Start End Public consultation not published not published Construction August 2026 Oct 2027 - Sources disagree
- The coordination feed gives construction starting 2026-07-20; Public Works' project page (Start “Summer, 2026”; text “August 2026”), 2026-08, which is shown.
- Records
- Public Works project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Various Locations Pavement Renovation No. 90 and Sewer Replacement9 Apr 2026 · Public Works Commission
6 decisions on the same streets, not naming this project
- Award Grant Agreement No. PRO.0300 (G), Demonstration Garden Programming and Maintenance to Earth Island Institute, acting as the fiscal sponsor for Garden for the Environment, to operate a public demonstration garden an…11 Mar 2025 · SFPUC Commission · approve the Consent Calendar Item Nos. 6a, 6b, and 6c
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Jules Avenue, west side, from 5 feet to 37 feet south of Ocean Avenue (32-foot station) (Supervisor District 11) (Approvable by the City Traffic Eng…6 Dec 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WD-2844, 12-Inch Ductile Iron Water Main Installation on Parnassus Avenue, from Stanyan Street to 6th Avenue, on Lawton Street from 7th Avenue to Funston Avenue, and Various Street Locations, to the re…24 Sep 2024 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 15th Avenue, north side, from 5 feet to 67 feet west of Portola Drive (62-foot bike share station) (Supervisor District 7) (Approvable by the City T…22 Mar 2024 · Engineering hearing · Item withdrawn.
- ESTABLISH – SIDEWALK BIKE SHARE STATION 14th Avenue, east side, from 5 feet to 78 feet south of Geary Boulevard (72 feet 6 inch bike share station with a 20-foot red zone daylighting at the northern end of the station) (…18 Aug 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 14th Avenue, east side, from Geary Boulevard to 82 feet southerly (72-foot bike share station with red zones on either side) (Supervisor District 1) …4 Oct 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published.
1 other projects on these street segments
- Various Locations Pavement Renovation No 90Public Works · Construction · 15 shared street segments
How we built this: About the Data