252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Pavement Renovation No 92
0% in published scope
Public Works · Repaving · Design · Starts 29 Mar 2027, ends 11 Jun 2028
All 5 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 24th St, 25th St, Alpha St, Appleton Ave, Argonaut Ave, Bennington St
- Planned bikeway
- Level 3 shared street, 0.43 mi on Holly Park Cir, Bocana St
- Would reach
- 1,694 residents (2020 census), 1 library would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 5 street segments that lack one. Closer in: 825 residents, 1 school with none within about one block (440 feet) today would have one; 1,745 residents with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Mar 2027 Jun 2028 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
3 decisions on the same streets, not naming this project
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Wisconsin Street, east side, from 10 feet to 19 feet south of Connecticut Street (Supervisor District 10) (Approvable by the City Traffic Engineer) Grant Brokl, [staff ema…18 Apr 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – RED ZONE A. 25th Street, south side, from Connecticut Street to 29 feet easterly (removes 1 parking space) B. 25th Street, south side, from 184 feet to 306 feet east of Connecticut Street (removes 6 parking s…8 Jul 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation. # (only 16(b) is reviewable by BOS)
- Approve an increase of 30 consecutive calendar days to the contract duration contingency for Contract No. WW-703, Mission Street, 16th to Cesar Chavez Street, Brick Sewer Rehabilitation; and authorize the General Manager…14 Dec 2021 · SFPUC Commission · approve Consent Calendar items 10a through 10g
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.
3 other projects on these street segments
- Visitacion Valley and Portola Community Based Transportation PlanSFMTA · Planning · 12 shared street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 4 shared street segments
- Pier 80 Electrificationother · Planning · 2 shared street segments
How we built this: About the Data