Cesar Chavez Bikeway Improvements Project
Builds 41%
SFMTA · Bike, walk or safety · Detailed Design · Starts Early 2027, ends 31 Dec 2028
7 of the project's 15 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 0.42 mi of the plan's bikeway.
- Streets
- Cesar Chavez St, Illinois St
- Planned bikeway
- Separated bikeway, 2.1 mi on Cesar Chavez St, Illinois St
- Scope
- On the project page
- Dates
Start End Public consultation Summer 2024-2026 Summer 2024-2026 Construction Early 2027 Dec 2028 - Sources disagree
- The coordination feed gives construction starting 2026-09-01; SFMTA's project page gives 2027, which is shown.
SFMTA gives the phase as Detailed Design; the coordination feed gives Design. - Records
- SFMTA project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
3 milestones and events from the project's own page
- ConstructionEarly 2027 · Project page timeline · Pending
- ApprovalsLate 2026 · Project page timeline · Pending
- Design & OutreachSummer 2024-2026 · Project page timeline · Pending
4 decisions on the same streets, not naming this project
- ESTABLISH – TOW–AWAY, NO PARKING ANY TIME A. Evans Avenue, south side, from Rankin Street to 193 feet easterly (removes 7 unmetered parking spaces in the vicinity of rail crossing) B. Evans Avenue, south side, from 483 f…14 Nov 2025 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Award Contract No. WW-790, Evans Ave. and Mariposa St. Outfalls Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $2,576,348, with a duration of 379 con…9 Sep 2025 · SFPUC Commission · approve the Consent Calendar
- Approve an increase of 30 consecutive calendar days to the contract duration contingency for Contract No. WW-703, Mission Street, 16th to Cesar Chavez Street, Brick Sewer Rehabilitation; and authorize the General Manager…14 Dec 2021 · SFPUC Commission · approve Consent Calendar items 10a through 10g
- 10(a). ESTABLISH – CLASS IV BIKEWAY A. Evans Avenue, south side, from Keith Street to Jennings Street B. Evan Avenue, both directions, from Jennings Street to Hunters Pt. Boulevard C. Hunters Point Boulevard, both direct…4 Dec 2020 · Engineering hearing · To be approved by the City Traffic Engineer for implementation after receipt of environmental clearance.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Bay Shore Blvd and Cesar Chavez Pavement RenovationPublic Works · Planning · 12 shared street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 9 shared street segments
- Bay Corridor Transmission and Distribution Phase 4 and Water ImprovementsSFPUC · Construction · 6 shared street segments
- Various Locations Pavement Renovation No 79Public Works · Design · 6 shared street segments
- Pier 80 Electrificationother · Planning · 3 shared street segments
- Cesar Chavez/Potrero Ave/Bayshore Blvd Intersection Improvements (The Hairball)SFMTA · Completed · 3 shared street segments
- Indiana Street Bikeway ProjectSFMTA · Completed · 2 shared street segments
- Channel Force Main IntertieSFPUC · Construction · 2 shared street segments
2 documents on the project page