Cesar Chavez Bikeway Improvements Project

Builds 41%

SFMTA · Bike, walk or safety · Detailed Design · Starts Early 2027, ends 31 Dec 2028

Early enough to change: SFMTA gives its phase as Detailed Design; its project page may list a contact. No meeting on it is posted for the next 60 days.

7 of the project's 15 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 0.42 mi of the plan's bikeway.

Streets
Cesar Chavez St, Illinois St
Planned bikeway
Separated bikeway, 2.1 mi on Cesar Chavez St, Illinois St
Scope
On the project page
Dates
StartEnd
Public consultationSummer 2024-2026Summer 2024-2026
ConstructionEarly 2027Dec 2028
Sources disagree
The coordination feed gives construction starting 2026-09-01; SFMTA's project page gives 2027, which is shown.
SFMTA gives the phase as Detailed Design; the coordination feed gives Design.
Records
SFMTA project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

3 milestones and events from the project's own page
4 decisions on the same streets, not naming this project

Construction on these street segments

20232024202520262027202820292030todayCesar Chavez Bikeway Improvements Pr…Channel Force Main IntertieBay Corridor Transmission and Distri…Various Locations Pavement Renovatio…Bay Shore Blvd and Cesar Chavez Pave…Channel Force Main Intertie: construction Jul 2023 to 31 Dec 2026Bay Corridor Transmission and Distribution Phase 4 and Water Improvements: construction Oct 2024 to 28 Feb 2026Various Locations Pavement Renovation No 79: construction Jan 2026 to 17 Nov 2026Bay Shore Blvd and Cesar Chavez Pavement Renovation: construction 9 Nov 2027 to 21 Jan 2029Cesar Chavez Bikeway Improvements Project: construction 2027 to 31 Dec 2028Jul 2023 – 31 Dec 2026Oct 2024 – 28 Feb 2026Jan 2026 – 17 Nov 20262027 – 31 Dec 20289 Nov 2027 – 21 Jan 2029

Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.

8 other projects on these street segments
2 documents on the project page

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.