Bay Corridor Transmission and Distribution Phase 4 and Water Improvements
0% in published scope
SFPUC · Sewer, water or power · Construction · Under way, ends 28 Feb 2026
1 of the project's 6 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- Cesar Chavez from Evans Avenue to Indiana
- Planned bikeway
- Separated bikeway, 0.75 mi on Cesar Chavez St
- Scope
- “The San Francisco Public Utilities Commission is extending the Bay Corridor Transmission & Distribution electrical system, upgrading aging low-pressure water infrastructure, and expanding the high-pressure Emergency Firefighting Water System to better serve the needs of existing and future customers in San Francisco’s Bayview neighborhood. UPDATE: AUGUST 2026 Our contractor is currently installing a new water main on Cesar Chavez from Evans Avenue to Indiana Street. This work is expected to last through the end of 2026. For information on what to expect during construction visit sfpuc.gov/NewW”
- Dates
Start End Public consultation not published not published Construction Fall 2024 Feb 2026 - Sources disagree
- SFPUC's project page's Start field gives construction starting 2024-10; SFPUC's project page text gives 2024-11 (“mid-November 2024”).
The published end date, 2026-02-28, has passed; SFPUC's project page (Project Phase) still gives it as Construction. - Records
- SFPUC project page
City decisions naming this project
- Approve an increase of $3,100,000 to the cost contingency and an increase of 260 calendar days to the duration contingency for Contract No. PW-011, Bay Corridor Transmission and Distribution Phase 4 and Water Improvement…24 Jun 2025 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. PW-011, Bay Corridor Transmission and Distribution Phase 4 and Water Improvements, to the responsible bidder that submitted the lowest responsive bid, Mitchell Engineering28 May 2024 · SFPUC Commission · continued
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
6 other projects on these street segments
- Cesar Chavez Bikeway Improvements ProjectSFMTA · Detailed Design · 7 shared street segments
- Bay Shore Blvd and Cesar Chavez Pavement RenovationPublic Works · Planning · 4 shared street segments
- Channel Force Main IntertieSFPUC · Construction · 2 shared street segments
- Dogpatch-Central Waterfront Area Transit Connections StudySFMTA · Current · 2 shared street segments
- Indiana Street Bikeway ProjectSFMTA · Completed · 1 shared street segment
- Evans Avenue Quick-BuildSFMTA · Completed · 1 shared street segment