Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Broad Street and Randolph Street Sewer Replacement

0% in published scope

Public Works · Sewer, water or power · Design · Under way, ends 1 Feb 2028

All 2 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
Arch St, Bright St, Broad St, Ramsell St, Randolph St
Planned bikeway
Shared street, 0.2 mi on Randolph St
Would reach
1,394 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 2,139 residents, 1 library with none within about one block (440 feet) today would have one; 1,825 residents, 1 school with none within about two blocks (880 feet) today would have one
Scope
“Broad Street, Randolph Street, and San Jose Avenue Sewer Replacement”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionMar 2022Feb 2028
Sources disagree
The coordination feed carries this job as 2 rows (row 61339 shares numbers 10038796 and WW-734 with row 61050) that disagree: row 61050, Design, 2022-03-15 to 2028-02-01; row 61339, Design, 2027-02-27 to 2027-11-04. The dates shown are row 61050's.
The start date has passed (2022-03-15) while the phase is still Design, per the coordination feed.
Records
Interagency coordination feed record (DataSF row) · Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Sewer Upgrades: Renewal & Replacement Program

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

1 decisions on the same streets, not naming this project

Construction on these street segments

20222023202420252026202720282029todayBroad Street and Randolph Street Sew…PW - M & J Lines - Muni Forward Proj…M Ocean View Transit and Safety Proj…PW As Needed Spot Sewer Replacement …Various Locations Spot Main Sewer Re…PW - M & J Lines - Muni Forward Project: construction 27 Dec 2023 to 1 Jan 2027M Ocean View Transit and Safety Project: construction Apr 2024 to 30 Nov 2025PW As Needed Spot Sewer Replacement No 47: construction 22 Sep 2025 to 26 Oct 2026Various Locations Spot Main Sewer Replacement No 2: construction 15 Mar 2027 to 12 Mar 2028Broad Street and Randolph Street Sewer Replacement: construction 15 Mar 2022 to 1 Feb 2028Apr 2024 – 30 Nov 202522 Sep 2025 – 26 Oct 202615 Mar 2027 – 12 Mar 202815 Mar 2022 – 1 Feb 202827 Dec 2023 – 1 Jan 2027

Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.

6 other projects on these street segments