Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
PW Various Locations Sewer Replacement No 31
Already built
Public Works · Sewer, water or power · Design · Starts 7 Jun 2027, ends 9 Jun 2028
1 of the project's 7 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 15th Ave, 16th Ave, 21st Ave, 25th Ave, 27th Ave, 29th Ave
- Planned bikeway
- Shared street, 0.71 mi on Golden Gate Ave, 15th Ave, Anza St, Lake St
- Would reach
- No one new would be within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's street segment that lack one. Closer in: 212 residents (2020 census) with none within about one block (440 feet) today would have one
- Scope
- “2596i, WW-778”
- Dates
Start End Public consultation not published not published Construction Jun 2027 Jun 2028 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Sewer Upgrades: Renewal & Replacement Program
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
6 decisions on the same streets, not naming this project
- ESTABLISH – RED ZONE ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES 25th Avenue North, north side, from 6 feet to 30 feet east of driveway at 4 25th Avenue North (Supervisor District 1) (Approvable by the City Traffic …18 Apr 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of 155 calendar days to the duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for SFPUC DECEMBER 10, 2024 MEETING MINUTES Page 6 of 1…10 Dec 2024 · SFPUC Commission · approve Item 13
- Approve an increase of 90 calendar days to the duration contingency and increase of $200,000 to the amount contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a…25 Jun 2024 · SFPUC Commission
- Approve an increase of 185 calendar days to the contract duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a new contract duration limit of up to 570…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 15th Avenue, north side, from 5 feet to 67 feet west of Portola Drive (62-foot bike share station) (Supervisor District 7) (Approvable by the City T…22 Mar 2024 · Engineering hearing · Item withdrawn.
- Approve the plans and specifications and award Contract No. WW-684, 45th, 46th, 47th Aves, Vicente, Wawona Streets and Sloat Blvd. Sewer Replacement, in the amount of $7,342,613, and with a duration of 375 consecutive ca…8 Nov 2022 · SFPUC Commission · approve the Consent Calendar, with the amendment to the date on the
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Slow StreetsSFMTA · Construction · 9 shared street segments
- WD-2936 8-, 12- & 16-inch Ductile Iron Water Main Replacement on Geary Boulevard from Stanyan Street to Presidio Avenue & on Post Street from Presidio Avenue to Scott Street & on Various Side StreetsSFPUC · Design · 3 shared street segments
- Laurel Heights/Jordan Park Traffic Calming ProjectSFMTA · Implementation / Construction · 2 shared street segments
- PEFWS Pipeline Contract C - 24-inch 42nd (between Lawton & Irving)SFPUC · Planning · 2 shared street segments
- Golden Gate Avenue Slow StreetSFMTA · 2 shared street segments
- PW As Needed Spot Sewer Replacement No 47Public Works · Construction · 2 shared street segments
- Various Locations Pavement Renovation No 81 and Sewer ReplacementPublic Works · Construction · 1 shared street segment
- PW Various Locations Sewer Replacement (JV VL PR No 81)Public Works · Construction · 1 shared street segment
How we built this: About the Data