Page Slow Street
Builds 80%
SFMTA · Bike, walk or safety · Planning · Under way, ends 31 Dec 2027
1 of the project's 20 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. SFMTA's bikeway layer and project page show it building or upgrading 2.9 mi of the plan's bikeway.
- Streets
- Page St
- Planned bikeway
- Shared street, 3.6 mi on Page St
- Scope
- On the project page
- Dates
Start End Public consultation 24 Aug 2022 Summer 2024 - Early 2026 Construction Sep 2026 Dec 2027 - Sources disagree
- The coordination feed gives construction ending 2028-12-31; SFMTA's project page gives 2027-12-31, which is shown.
The start date has passed (2026-09-01) while the phase is still Planning, per SFMTA's project layer.
SFMTA gives the phase as Planning; the coordination feed gives Design. - Records
- SFMTA project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- ESTABLISH – TOW-AWAY, NO STOPPING ANYTIME – Page Street17 Jan 2023 · SFMTA Board · ADOPTED — 4 ayes (Resolution 230117-010)
- ESTABLISH -- NO LEFT TURN Divisadero Street, southbound, at Page Street Divisadero Street, northbound, at Page Street 22(b). ESTABLISH -- RIGHT TURN ONLY, EXCEPT BICYCLES Page Street, westbound, at Divisadero Street Page…19 Aug 2022 · Engineering hearing · Revised approval path. Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
7 milestones and events from the project's own page
- Construction2027+ · Project page timeline · Pending
- ApprovalsSummer 2026 · Project page timeline · Pending
- Design & Early Implementation2026-2027 · Project page timeline · Pending
- OutreachSummer 2024 - Early 2026 · Project page timeline · Pending
- Board of Directors meeting, January 17, 202317 Jan 2023 · Project page event
- Page Slow Street Outdoor Office Hours24 Aug 2022 · Project page event
- Engineering Public Hearing Meeting, August 19, 202219 Aug 2022 · Project page event
25 decisions on the same streets, not naming this project
- ESTABLISH – SIDEWALK BIKESHARE STATION Laguna Street, east side, from 19 feet to 71 feet north of Turk Street (Supervisor District 5) (Approvable by the City Traffic Engineer)4 Sep 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKESHARE STATION Page Street, north side, from Fillmore Street to 20 feet easterly (in existing red zone) Fillmore Street, west side, from Page Street to 21 feet nort…24 Jul 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Accept work performed by M. Squared Construction, Inc., under Contract No. WD- 2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street; approve Modification No. 3 (Final) dec…10 Nov 2025 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. WW-757R, Laguna, Howard, and Mission Creek Combined Sewer Discharge Improvements, to the responsible bidder that submitted the lowest responsive bid, Pullman SST, Inc., in the amount of $7,296,786, wit…13 May 2025 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO PARKING ANYTIME, EXCEPT BICYCLES Webster Street, east side, from 11 feet to 29 feet south of Sutter Street (Supervisor District 5) (Approvable by the City Traffic Engineer) Carmen Leung, [staff email remov…17 Jan 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WD-2844, 12-Inch Ductile Iron Water Main Installation on Parnassus Avenue, from Stanyan Street to 6th Avenue, on Lawton Street from 7th Avenue to Funston Avenue, and Various Street Locations, to the re…24 Sep 2024 · SFPUC Commission · approve the Consent Calendar
- Award Contract No. WW-743, Geary Boulevard Sewer and Water Improvements Phase 2, to the responsible bidder that submitted the lowest responsive bid, Cratus, Inc., in the amount of $45,957,035, and with a duration of 1,03…25 Jun 2024 · SFPUC Commission
- ESTABLISH – NO PARKING ANYTIME, EXCEPT BICYCLES Octavia Street, east side, from 15 feet to 25 feet south of Oak Street (Supervisor District 5) (Approvable by the City Traffic Engineer) Carmen Leung, [staff email removed …14 Jun 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Laguna Street, east side, from 5 feet to 15 feet south of Hayes Street (Supervisor District 5) (Approvable by the City Traffic Engineer) Carmen Leung, [staff email removed…19 Jan 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street, to the responsible bidder that submitted the lowest responsive bid, M. Squared Construction, In…9 Jan 2024 · SFPUC Commission · approve items 6a through 6i
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Page Street, south side, from Cole Street to 70 feet easterly (Supervisor District 5) (Approvable by the City Traffic Engineer) Laura Stonehill, [sta…19 May 2023 · Engineering hearing · On hold for further outreach at this location and to investigate other potential locations.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Laguna Street, west side, from Grove Street to 86 feet northerly (Supervisor District 5) (Approvable by the City Traffic Engineer) Laura Stonehill, […19 Aug 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO RIGHT TURN, EXCEPT BICYCLES Stanyan Street, northbound, at Page Street (Approvable by the City Traffic Engineer) 12(b). ESTABLISH – NO LEFT TURN, EXCEPT BICYCLES Stanyan Street, southbound, at Page Street …8 Jul 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – RIGHT OR LEFT TURN ONLY, EXCEPT BICYCLES Page Street, eastbound, at Masonic Avenue (Approvable by the City Traffic Engineer) 11(b). ESTABLISH – NO RIGHT TURN, EXCEPT BICYCLES Masonic Avenue, northbound, at Pa…8 Jul 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO TURN ON RED Webster Street, northbound and southbound, at Geary Boulevard (Supervisor District 5) (Approvable by the City Traffic Engineer) Daniel Mackowski, [staff email removed — see the order] These veh…13 Aug 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- Accept work performed by Cratus, Inc. for Contract No. WD-2614, 8-Inch Ductile Iron Water Main Replacement on Green Street from Gough Street to Broderick Street; approve Modification No. 2 (Final), decreasing the contrac…8 Jun 2021 · SFPUC Commission · approve the Consent Calendar 8a through 8e
- Amending Transportation Code, Division II, Section 702 to reduce the speed limit on Market Street between Franklin Street and Steuart Street - designate a transit-only lane on Market Street RESCIND - RIGHT TURN ONLY, EXC…19 Jan 2021 · SFMTA Board · ADOPTED — 5 ayes, 2 nays
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Page Street, south side, from Masonic Avenue to 90 feet easterly (82-foot station with red zones either side) (Supervisor District 5) Daniel Carr, [s…4 Dec 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- RESCIND--TWO HOUR PARKING, MONDAY THROUGH FRIDAY, 8 AM TO 9 PM, EXCEPT VEHICLES WITH AREA S PERMITS (retains RPP eligibility) Laguna Street, east side, between Hayes Street and Linden Street (Supervisor District 5) Kathr…12 Jun 2020 · Engineering hearing · Approved by City Traffic Engineer to send to the SFMTA Board for approval and implementation. # Sustainable Streets Division
- Motion directing the Clerk of the Board to prepare findings reversing the determination by the Planning Department that the proposed San Francisco Municipal Transportation Agency Page Street Bikeway Improvements Pilot Pr…4 Feb 2020 · Board of Supervisors · Killed
- Motion conditionally reversing the determination by the Planning Department that the San Francisco Municipal Transportation Agency Page Street Bikeway Improvements Pilot Project is categorically exempt from further envir…4 Feb 2020 · Board of Supervisors · Killed
- Motion affirming the determination by the Planning Department that the proposed San Francisco Municipal Transportation Agency Page Street Bikeway Improvements Pilot Project is categorically exempt from further environmen…4 Feb 2020 · Board of Supervisors · Passed
- Hearing of persons interested in or objecting to the determination of exemption from environmental review under the California Environmental Quality Act issued as a Categorical Exemption by the Planning Department on Sep…4 Feb 2020 · Board of Supervisors · Filed
- ESTABLISH – 2-HOUR PARKING, 8 AM TO 9 PM, MONDAY THROUGH FRIDAY, EXCEPT VEHICLES WITH AREA S PERMITS A. Webster Street, east side, between Page Street and Haight Street B. Haight Street, north side, between Webster Stree…6 Dec 2019 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation. # Public Comments: No comments received.
- Approving a 15-month Page Street Bikeway Improvement pilot project, starting approximately February 1, 2020; establishing Class II, Class III and Class IV bicycle facilities on Page Street; adding a peak period right-tur…19 Nov 2019 · SFMTA Board · ADOPTED — 7 ayes
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- 14-009 8-, and 24-inch Ductile Iron Water Main Replacement on Page Street from Stanyan to Fillmore StreetsSFPUC · Design · 29 shared street segments
- Octavia Boulevard Enhancement ProgramSFMTA · Current · 9 shared street segments
- Page Street Neighborway ProjectPublic Works · In progress · 7 shared street segments
- Mission District Sewer Rehabilitation (VLLD2B)Public Works · Design · 3 shared street segments
- Wiggle Neighborhood Green CorridorSFMTA · Completed · 3 shared street segments
- Golden Gate Park Traffic Safety ProjectSFMTA · Completed · 2 shared street segments
- Western Addition Community Based Transportation Plan ImplementationSFMTA · Current · 2 shared street segments
- Better Market StreetSFMTA · Current · 2 shared street segments