252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Sewer Replacement No 29
Already built
Public Works · Sewer, water or power · Design · Starts 12 Jun 2027, ends 13 Dec 2028
The project's one street segment on a planned bikeway street already has an all-ages bikeway.
- Streets
- 16th St, 17th St, Albion St, Avila St, Baker St, Beach St
- Planned bikeway
- Shared street, 0.18 mi on Golden Gate Ave
- Scope
- “2563i”
- Dates
Start End Public consultation not published not published Construction Jun 2027 Dec 2028 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Sewer Upgrades: Renewal & Replacement Program
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
20 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKESHARE STATION Beach Street, north side, from Divisadero Street to 20 feet easterly (in existing red zone) Divisadero Street, east side, from Beach Street to 21 fee…24 Jul 2026 · Engineering hearing · On hold.
- Accept work performed by M. Squared Construction, Inc., under Contract No. WD- 2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street; approve Modification No. 3 (Final) dec…10 Nov 2025 · SFPUC Commission · approve the Consent Calendar
- Approving various parking and traffic modifications along Beach Street between Van Ness Avenue and The Embarcadero to improve transportation safety and connectivity17 Dec 2024 · SFMTA Board · ADOPTED — 6 ayes (Resolution 241217-146)
- Approve an increase of 155 calendar days to the duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for SFPUC DECEMBER 10, 2024 MEETING MINUTES Page 6 of 1…10 Dec 2024 · SFPUC Commission · approve Item 13
- RESCIND – CLASS III BIKE LANE Baker Street, southbound, from Fell Street to Oak Street 38(b). RESCIND – ANGLED PARKING ESTABLISH – PARALLEL PARKING Baker Street, west side, between Oak Street and Fell Street 38(c). ESTAB…8 Nov 2024 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- RESCIND – CLASS III BIKE LANE Baker Street, southbound, from Fell Street to Oak Street 8(b). RESCIND – ANGLED PARKING ESTABLISH – PARALLEL PARKING Baker Street, west side, between Oak Street and Fell Street 8(c). ESTABLI…18 Oct 2024 · Engineering hearing · Item withdrawn by staff.
- ESTABLISH – SPEED CUSHIONS Noe Street, between 14th Street and Henry Street (1 3-lump cushion) Noe Street, between 15th Street and Beaver Street (1 3-lump cushion) 5(b). RESCIND – GREEN ZONE ESTABLISH – RED ZONE Noe Stre…16 Aug 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of 90 calendar days to the duration contingency and increase of $200,000 to the amount contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a…25 Jun 2024 · SFPUC Commission
- Approve an increase in the amount of $450,000 to the cost contingency and an increase of 60 calendar days to the duration contingency for Contract No. WD-2843, 16-, 12-, and 8-Inch Ductile Iron Water Main Replacement on …14 May 2024 · SFPUC Commission
- Award Contract No. WD-2765, 8-Inch and 16-Inch Ductile Iron Water Main Replacement on Jersey Street from Douglass Street to Church Street and Various Street Locations, to the responsible bidder that submitted the lowest …9 Apr 2024 · SFPUC Commission · approve the Consent Calendar
- Approve an increase of 185 calendar days to the contract duration contingency for Contract No. WW-705, Various Locations Sewer Replacement No. 10, with Mitchell Engineering, for a new contract duration limit of up to 570…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- Approving parking and traffic modifications along 17th Street between Potrero Avenue and Mississippi Street to improve transportation safety and connectivity5 Mar 2024 · SFMTA Board · ADOPTED — 7 ayes (Resolution 240305-020)
- Accept work performed by Trinet Construction, Inc. for Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair; approve Modification No. 1 (Final) decreasing the Contract amoun…23 Jan 2024 · SFPUC Commission · approve items 7a through 7i
- Award Contract No. WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street, to the responsible bidder that submitted the lowest responsive bid, M. Squared Construction, In…9 Jan 2024 · SFPUC Commission · approve items 6a through 6i
- ESTABLISH – CLASS IV BIKEWAY 17th Street, eastbound and westbound, between Potrero Avenue and Mississippi Street (Approvable by the City Traffic Engineer) 4(b). ESTABLISH – STOP SIGNS 17th Street, eastbound and westbound…1 Sep 2023 · Engineering hearing · Item 4(a) corrected to reflect approvability by the City Traffic Engineer. Item 4(c) updated to TOW AWAY NO STOPPING ANY TIME as originally proposed. Items 4(a) through 4(s) approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Award Contract No. WW-737, Baker St. Combined Sewer Discharge Baffle Improvements & Backflow Valve Repair, in the amount of $566,000, and with a duration of 240 consecutive calendar days, to the responsible bidder that s…10 Jan 2023 · SFPUC Commission · Approve Consent Calendar Items 6a through 6j
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION North Point Street, north side, from 141 feet to 225 feet east of Powell Street (75-foot bike share station with red zones on either side) (Approvabl…18 Jun 2021 · Engineering hearing · Approved by the City Traffic Engineer for implementation. #
- Accept work performed by Cratus, Inc. for Contract No. WD-2614, 8-Inch Ductile Iron Water Main Replacement on Green Street from Gough Street to Broderick Street; approve Modification No. 2 (Final), decreasing the contrac…8 Jun 2021 · SFPUC Commission · approve the Consent Calendar 8a through 8e
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Fillmore Street, east side along median, from Jefferson Street to 53 feet southerly (bike share station in angled parking stalls) (Supervisor Distric…17 Jul 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation. Public Comments: Received comments in support and opposition.
- ESTABLISH – SPEED TABLES 17th Street, between Market Street and Diamond Street (2 speed tables) 17(b). ESTABLISH – CROSSWALK 17th Street, midblock between Diamond Street and Castro Street 17(c). ESTABLISH – CLASS IV BIKE…18 Oct 2019 · Engineering hearing · Approved by the City Traffic Engineer to send to SFMTA Board for legislation. Public Comments: Comments received in opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 4 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Slow StreetsSFMTA · Construction · 5 shared street segments
- Various Locations Pavement Renovation No 86BPublic Works · Planning · 3 shared street segments
- Western Addition Community Based Transportation Plan ImplementationSFMTA · Current · 3 shared street segments
- Joint - MTA Lead - Fillmore St Pavement Renovation Phase 2Public Works · Planning · 3 shared street segments
- Mission District Sewer Rehabilitation (VLLD2B)Public Works · Design · 2 shared street segments
- Various Locations Pavement Renovation Concrete No 93Public Works · Planning · 2 shared street segments
- Castro St and Divisadero St Pavement Renovation ProjectPublic Works · Planning · 2 shared street segments
- Street Resurfacing Program- BBSR Paving FY 26-27Public Works · Construction · 2 shared street segments