Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Sutter Street Safety Project
No known overlap
SFMTA · Bike, walk or safety · Planning · Under way, ends 31 Dec 2025
None of the project's street segments is on the Biking and Rolling Plan's network. It is listed because SFMTA tags the project Bike.
- Streets
- Sutter St
- Planned bikeway
- Nothing on these street segments.
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Nov 2025 December 2025 - Sources disagree
- The start date has passed (2025-11) while the phase is still Planning, per SFMTA's project layer.
The published end date, 2025-12-31, has passed; SFMTA's project layer still gives it as Planning. - Not yet checked
- The construction end shown, 2025-12-31, was read from the words “December 2025” on SFMTA's project page by a model, and a person has not confirmed it.
- Records
- SFMTA project page
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
5 other projects on these street segments
- Western Addition Community Based Transportation Plan ImplementationSFMTA · Current · 6 shared street segments
- PLN 2526-001: 8-inch Ductile Iron Water Main Replacement on Sutter from Divisadero to Webster, on Pine from Pierce to Gough St, and Various Side StreetsSFPUC · Planning · 4 shared street segments
- Various Locations Pavement Renovation Under Overhead Contact System No 2Public Works · Planning · 3 shared street segments
- Sutter St and Post St Pavement RenovationPublic Works · Design · 2 shared street segments
- Joint - MTA Lead - Fillmore St Pavement RenovationPublic Works · Planning · 2 shared street segments